306 E BARBOUR ST 90293
Certificate Information: 306 E BARBOUR ST 90293
- Application / Permit
- 25047-10000-00721
- Plan Check / Job No.
- B25LA24519
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- EPLAN.NEW pool, baja, and spa, per standard plan
- Permit Issued
- Issued on 3/12/2026
- Issuing Office
- Current Status
- CofO Issued on 6/29/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/12/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 6/18/2025 | MARCELA FRANQUEZ |
| Corrections Issued | 6/21/2025 | MARCELA FRANQUEZ |
| Quality Review Completed | 6/27/2025 | TU HUA |
| Plan Check Approved | 1/21/2026 | MARCELA FRANQUEZ |
| Issued | 3/12/2026 | APPLICANT |
| CofO in Progress | 6/26/2026 | MICHAEL LEWIS |
| Permit Finaled | 6/29/2026 | JUAN VALENZUELA |
| CofO Issued | 6/29/2026 | JUAN VALENZUELA |
| Permit Finaled | 6/29/2026 | JUAN VALENZUELA |
Permit Application Clearance Information
| ZA Case | Cleared | 8/4/2025 | DALIA MOKAYED |
| Construction near power lines | Cleared | 9/5/2025 | RIDWAN HARDY |
| Coastal Zone | Cleared | 10/7/2025 | DALIA MOKAYED |
| Grading Pre-Inspection | Cleared | 11/3/2025 | MARCELA FRANQUEZ |
Contact Information
| Architect | Dembsky,, Amit; Lic. No.: NA30383 | , |
| Contractor | C I D Builders And Developers Inc; Lic. No.: 958193-B | , |
| Engineer | Lacher,, Todd Lee; Lic. No.: NA67656 | , |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pool Piping | 4/22/2026 | Approved | JESUS PINEDA |
| Pre-Gunite | 4/22/2026 | Approved | JESUS PINEDA |
| Deputy Shotcrete | 4/27/2026 | Conditional Approval | JESUS PINEDA |
| Deck | 6/1/2026 | Approved | MORRIS JACKSON |
| Enclosure/Fence | 6/1/2026 | Approved | MORRIS JACKSON |
| Special/Order Compliance | 6/1/2026 | Corrections Issued | MORRIS JACKSON |
| Notice of Violation | 6/9/2026 | Not Required | MICHAEL LEWIS |
| Excavation/Setback/Form/Re-Bar | 6/12/2026 | Approved | MICHAEL LEWIS |
| Final | 6/12/2026 | Corrections Issued | MICHAEL LEWIS |
| Green Building Final | 6/12/2026 | Approved | MICHAEL LEWIS |
| SGSOV-Seismic Gas S/O Valve | 6/12/2026 | SGSOV Approved | MICHAEL LEWIS |
| Equipment Noise Level | 6/16/2026 | Approved | BRIAN CHRISTIAN |
| Final | 6/25/2026 | OK to Issue CofO | MICHAEL LEWIS |