1693 N STONE CANYON ROAD 90077
Certificate Information: 1693 N STONE CANYON ROAD 90077
- Application / Permit
- 25047-10000-00377
- Plan Check / Job No.
- B25LA12388
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- [ePlan] New POOL/ SPA PER STANDARD PLAN #268
- Permit Issued
- Issued on 7/28/2025
- Issuing Office
- Current Status
- CofO Issued on 5/20/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/1/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 4/17/2025 | MAHNAZ NOURHASHEMI |
| Corrections Issued | 4/22/2025 | MAHNAZ NOURHASHEMI |
| Quality Review Completed | 5/2/2025 | GARO TELMI |
| Applicant returned to address corrections | 5/21/2025 | MAHNAZ NOURHASHEMI |
| Applicant returned to address corrections | 6/24/2025 | MAHNAZ NOURHASHEMI |
| Plan Check Approved | 7/22/2025 | MAHNAZ NOURHASHEMI |
| Issued | 7/28/2025 | APPLICANT |
| CofO in Progress | 5/14/2026 | RYAN SALAZAR |
| CofO in Progress | 5/14/2026 | RYAN SALAZAR |
| Permit Finaled | 5/20/2026 | RICHARD STEINBACH |
| Permit Finaled | 5/20/2026 | RICHARD STEINBACH |
| CofO Issued | 5/20/2026 | RICHARD STEINBACH |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 6/27/2025 | LANNY MERRICK |
Contact Information
| Contractor | California Poolman; Lic. No.: 1072732-C53 | , |
Inspector Information
| RYAN SALAZAR, (310) 914-3862 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 8/4/2025 | Corrections Issued | CHRISTOPHER WILSON |
| Gas Piping or Gas Test | 8/4/2025 | Corrections Issued | CHRISTOPHER WILSON |
| Pool Piping | 8/4/2025 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Pre-Gunite | 8/4/2025 | Corrections Issued | CHRISTOPHER WILSON |
| Special/Order Compliance | 8/13/2025 | Corrections Issued | MICHAEL PELHAM |
| Pre-Gunite | 10/24/2025 | Corrections Issued | SEAN HAUPT |
| Pre-Gunite | 10/29/2025 | Not Ready for Inspection | SEAN HAUPT |
| Deck | 2/2/2026 | Corrections Issued | CHRISTOPHER WILSON |
| Deck | 3/4/2026 | Approved | CHRISTOPHER WILSON |
| Enclosure/Fence | 3/31/2026 | Corrections Issued | CHRISTOPHER WILSON |
| Enclosure/Fence | 4/15/2026 | Approved | CHRISTOPHER WILSON |
| Final | 4/28/2026 | Corrections Issued | CHRISTOPHER WILSON |
| SGSOV-Seismic Gas S/O Valve | 4/28/2026 | SGSOV Approved | CHRISTOPHER WILSON |
| Final | 5/14/2026 | Partial Approval | RYAN SALAZAR |
| Pool Equipment Noise Test | 5/19/2026 | Approved | MIKE WANG |