3764 N BERRY DR 91604
Certificate Information: 3764 N BERRY DR 91604
- Application / Permit
- 25047-10000-00344
- Plan Check / Job No.
- B25LA11096
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- Eplan. NEW POOL/SPA PER STANDARD PLAN #268
- Permit Issued
- Issued on 7/22/2025
- Issuing Office
- Current Status
- CofO Issued on 1/27/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/24/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 3/27/2025 | JAD BASMA |
| Corrections Issued | 3/30/2025 | JAD BASMA |
| Quality Review Completed | 4/2/2025 | GARO TELMI |
| Applicant returned to address corrections | 5/2/2025 | JAD BASMA |
| Plan Check Approved | 6/4/2025 | JAD BASMA |
| Issued | 7/22/2025 | APPLICANT |
| CofO in Progress | 1/6/2026 | CHRISTOPHE COCHRAN |
| Permit Finaled | 1/27/2026 | RUBEN SALAS |
| CofO Issued | 1/27/2026 | RUBEN SALAS |
| Permit Finaled | 1/27/2026 | RUBEN SALAS |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 7/22/2025 | JAD BASMA |
Contact Information
| Contractor | Addison Pools Inc; Lic. No.: 753417-B | , |
Inspector Information
| CHRISTOPHE COCHRAN, (818) 374-1165 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 7/31/2025 | Approved | CHRISTOPHE COCHRAN |
| Pre-Gunite | 8/8/2025 | Corrections Issued | CHRISTOPHE COCHRAN |
| Pre-Gunite | 8/13/2025 | Partial Approval | CHRISTOPHE COCHRAN |
| Deputy Other (see comments) | 8/15/2025 | Conditional Approval | RAUL OLAGI |
| Grounding or Bonding | 8/25/2025 | Approved | CHRISTOPHE COCHRAN |
| Pool Piping | 8/25/2025 | Approved | CHRISTOPHE COCHRAN |
| Pre-Gunite | 8/25/2025 | Approved | CHRISTOPHE COCHRAN |
| Rough-Electrical | 8/25/2025 | Approved | CHRISTOPHE COCHRAN |
| Deputy Shotcrete | 8/27/2025 | Conditional Approval | JUAN VALENZUELA |
| Gas Piping or Gas Test | 9/15/2025 | Approved | CHRISTOPHE COCHRAN |
| Enclosure/Fence | 11/10/2025 | Approved | CHRISTOPHE COCHRAN |
| Excavation/Setback/Form/Re-Bar | 12/22/2025 | Approved | CHRISTOPHE COCHRAN |
| Final | 12/22/2025 | Corrections Issued | CHRISTOPHE COCHRAN |
| SGSOV-Seismic Gas S/O Valve | 12/22/2025 | SGSOV Approved | CHRISTOPHE COCHRAN |
| Equipment Noise Level | 12/30/2025 | Approved | AGUSTIN ALVAREZMORALES |
| Final | 1/6/2026 | OK to Issue CofO | CHRISTOPHE COCHRAN |