2795 N LA CASTANA DR 90046

Certificate Information: 2795 N LA CASTANA DR 90046

Application / Permit
25047-10000-00316
Plan Check / Job No.
B25LA10371
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
New pool per city of Los Angeles standard plan # 242 1 of 2
Permit Issued
Issued on 5/8/2025
Issuing Office
Valley
Current Status
Issued on 5/8/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 3/18/2025 APPLICANT
Assigned to Plan Check Engineer 3/21/2025 MINA HABILI
Corrections Issued 3/23/2025 MINA HABILI
Building Plans Picked Up 3/27/2025 APPLICANT
Applicant returned to address corrections 4/17/2025 DANIEL SMILEY
Plan Check Approved 5/1/2025 ZAW HAN
Issued 5/8/2025 APPLICANT

Permit Application Clearance Information

Grading Pre-Inspection Cleared 3/24/2025 MINA HABILI
Miscellaneous Cleared 4/21/2025 NATHAN ROMINE
Specific Plan Cleared 4/21/2025 NATHAN ROMINE
ZA Case Cleared 4/21/2025 NATHAN ROMINE
Eng Process Fee Ord 176,300 Cleared 4/29/2025 CINDY QI
Miscellaneous Cleared 4/30/2025 ALBERT TAM

Contact Information

Contractor Owner-Builder       ,
Engineer Oruncakciel,, Sayat; Lic. No.: C77182 15445 VENTURA BLVD 25      SHERMAN OAKS, CA 91403
Engineer Shniderman,, Jason Bernard; Lic. No.: C20524 16000 SHERMAN WAY #234      VAN NUYS, CA 91607

Inspector Information

ROY SPAULDING, (213) 202-3461 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 7/22/2025 Partial Approval ROY SPAULDING
Gas Piping or Gas Test 7/31/2025 Not Ready for Inspection BRIAN SULLIVAN
Pre-Gunite 7/31/2025 Corrections Issued BRIAN SULLIVAN
Rough-Electrical 7/31/2025 Approved BRIAN SULLIVAN
Rough-Plumbing 7/31/2025 Approved BRIAN SULLIVAN
Grading Pre-Inspection 8/2/2025 Off-Hour Fees Due
Pre-Gunite 8/13/2025 Approved BRIAN SULLIVAN
Deck 8/19/2025 Corrections Issued BRIAN SULLIVAN
SGSOV-Seismic Gas S/O Valve 8/19/2025 SGSOV Approved BRIAN SULLIVAN
Enclosure/Fence 8/26/2025 Corrections Issued BRIAN SULLIVAN
Grounding or Bonding 8/26/2025 Corrections Issued BRIAN SULLIVAN
Enclosure/Fence 8/28/2025 Approved ROY SPAULDING
Grounding or Bonding 8/28/2025 Approved ROY SPAULDING
Final 9/3/2025 Corrections Issued ROY SPAULDING
Pool Equipment Noise Test 9/4/2025 Approved MIKE WANG
Final 9/5/2025 Conditional Approval BRIAN SULLIVAN