1206 N AMALFI DR 90272
Certificate Information: 1206 N AMALFI DR 90272
- Application / Permit
- 25047-10000-00188
- Plan Check / Job No.
- B25LA05956
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- (E) POOL REMODEL DEMO (E) BENCH AND SPA ADD (N) AUTO COVER (N) SKIMMER, (N) SPA WITHIN (8X8) (17'X31' POOL) REPLACE POOL EQUIP SAME LOCATION WITH ENG CALCULATION
- Permit Issued
- Issued on 4/7/2025
- Issuing Office
- Current Status
- CofO Issued on 11/6/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/14/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 2/18/2025 | ADAM HEGAZI |
| Corrections Issued | 2/20/2025 | ADAM HEGAZI |
| Building Plans Picked Up | 3/6/2025 | APPLICANT |
| Applicant returned to address corrections | 4/3/2025 | DANIEL YIP |
| Plan Check Approved | 4/7/2025 | TSE MING HUANG |
| Issued | 4/7/2025 | APPLICANT |
| Permit Finaled | 11/6/2025 | RICHARD STEINBACH |
| CofO Issued | 11/6/2025 | RICHARD STEINBACH |
| Permit Finaled | 11/6/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 4/7/2025 | SERGIO VALENZUELA |
Contact Information
| Contractor | Clearflo Pools Construction; Lic. No.: 833846-C53 | 29669 AGOURA RD AGOURA HILLS, CA 91301 |
| Engineer | Biedenbach,, Christopher James; Lic. No.: C74003 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| KEVIN SARGSYAN, (310) 914-3889 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Gunite | 5/12/2025 | Corrections Issued | HERBERT GIRON |
| Pre-Gunite | 5/13/2025 | Corrections Issued | HERBERT GIRON |
| Pool Piping | 5/15/2025 | Approved | HERBERT GIRON |
| Pre-Gunite | 5/15/2025 | Conditional Approval | HERBERT GIRON |
| Deck | 6/5/2025 | Approved | HERBERT GIRON |
| Grounding or Bonding | 6/5/2025 | Approved | HERBERT GIRON |
| Pre-Gunite | 6/5/2025 | Approved | HERBERT GIRON |
| Enclosure/Fence | 8/14/2025 | Not Ready for Inspection | HERBERT GIRON |
| Enclosure/Fence | 8/18/2025 | Corrections Issued | MEL KHACHATOURIAN |
| Enclosure/Fence | 8/20/2025 | Corrections Issued | STEPHANIE SWANSON |
| Enclosure/Fence | 8/21/2025 | Not Ready for Inspection | HERBERT GIRON |
| Enclosure/Fence | 8/25/2025 | Approved | STEPHANIE SWANSON |
| Final | 9/9/2025 | Corrections Issued | HERBERT GIRON |
| SGSOV-Seismic Gas S/O Valve | 9/9/2025 | SGSOV Approved | HERBERT GIRON |
| Equipment Noise Level | 9/11/2025 | Approved | EUSEBIO GUZMAN |
| Final | 10/9/2025 | Conditional Approval | KENNETH NAGLE |
| Final | 10/28/2025 | Conditional Approval | KEVIN SARGSYAN |