7200 S ARIZONA AVE 90045
Certificate Information: 7200 S ARIZONA AVE 90045
- Application / Permit
- 25047-10000-00126
- Plan Check / Job No.
- B24LA38611
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- ePlan. REMODEL (E) POOL TO CREATE A 24'X40' POOL WITH (N) POOL COVER AND REPLASTER PER CITY STANDARD PLAN #268 AND ENGINEERING DETAILS
- Permit Issued
- Issued on 5/6/2025
- Issuing Office
- Current Status
- CofO Issued on 1/17/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/4/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 2/7/2025 | KAMYAR EMAMI |
| Corrections Issued | 2/10/2025 | KAMYAR EMAMI |
| Plan Check Approved | 3/12/2025 | MOHAMMAD ESMAILI |
| Issued | 5/6/2025 | APPLICANT |
| CofO in Progress | 1/14/2026 | ANTHONY EGSON |
| Permit Finaled | 1/17/2026 | RICHARD STEINBACH |
| CofO Issued | 1/17/2026 | RICHARD STEINBACH |
| Permit Finaled | 1/17/2026 | RICHARD STEINBACH |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 3/12/2025 | KAMYAR EMAMI |
Contact Information
| Contractor | Executive Pools Inc; Lic. No.: 1047519-C53 | , |
Inspector Information
| MORRIS JACKSON, (310) 914-3885 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 7/8/2025 | Approved | RUBEN RIVAS |
| Gas Piping or Gas Test | 7/8/2025 | Not Ready for Inspection | RUBEN RIVAS |
| Grounding or Bonding | 7/8/2025 | Corrections Issued | RUBEN RIVAS |
| Pool Piping | 7/8/2025 | Approved | RUBEN RIVAS |
| Pre-Gunite | 7/8/2025 | Not Ready for Inspection | RUBEN RIVAS |
| Rough-Electrical | 7/8/2025 | Not Ready for Inspection | RUBEN RIVAS |
| Rough-Plumbing | 7/8/2025 | Approved | RUBEN RIVAS |
| Deputy Drilled-In Anchors | 7/10/2025 | Conditional Approval | DAVID FEILER |
| Excavation/Setback/Form/Re-Bar | 7/11/2025 | Approved | RUBEN RIVAS |
| Gas Piping or Gas Test | 7/11/2025 | Corrections Issued | RUBEN RIVAS |
| Grounding or Bonding | 7/11/2025 | Approved | RUBEN RIVAS |
| Pool Piping | 7/11/2025 | Approved | RUBEN RIVAS |
| Pre-Gunite | 7/11/2025 | Approved | RUBEN RIVAS |
| Pre-Inspection | 7/11/2025 | Approved | RUBEN RIVAS |
| Rough-Electrical | 7/11/2025 | Partial Approval | RUBEN RIVAS |
| Rough-Plumbing | 7/11/2025 | Approved | RUBEN RIVAS |
| Gas Piping or Gas Test | 7/22/2025 | Approved | RUBEN RIVAS |
| Pre-Inspection | 9/23/2025 | Corrections Issued | RUBEN RIVAS |
| Enclosure/Fence | 11/24/2025 | Corrections Issued | ANTHONY EGSON |
| Special/Order Compliance | 11/24/2025 | Not Ready for Inspection | ANTHONY EGSON |
| Enclosure/Fence | 12/4/2025 | Approved | ANTHONY EGSON |
| Final | 1/5/2026 | Corrections Issued | ANTHONY EGSON |
| Pool/Spa Cover | 1/5/2026 | Corrections Issued | ANTHONY EGSON |
| SGSOV-Seismic Gas S/O Valve | 1/5/2026 | SGSOV Approved | ANTHONY EGSON |
| Final | 1/7/2026 | Corrections Issued | ANTHONY EGSON |
| Pool/Spa Cover | 1/7/2026 | Approved | ANTHONY EGSON |
| Final | 1/13/2026 | OK to Issue CofO | ANTHONY EGSON |