1460 N SAN REMO DR 90272

Certificate Information: 1460 N SAN REMO DR 90272

Application / Permit
25047-10000-00121
Plan Check / Job No.
B25LA03695
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
*ePlan* New pool with spa per engineered design
Permit Issued
Issued on 6/12/2025
Issuing Office
Current Status
Issued on 6/12/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 1/31/2025 APPLICANT
Assigned to Plan Check Engineer 2/6/2025 MATTHEW TORRES
Corrections Issued 2/8/2025 MATTHEW TORRES
Quality Review Completed 2/13/2025 HERNAN ARREOLA
Applicant returned to address corrections 4/25/2025 MATTHEW TORRES
Applicant returned to address corrections 6/5/2025 MATTHEW TORRES
Plan Check Approved 6/6/2025 MATTHEW TORRES
No Progress 6/10/2025 MATTHEW TORRES
Plan Check Approved 6/10/2025 MATTHEW TORRES
Issued 6/12/2025 APPLICANT

Permit Application Clearance Information

Miscellaneous Cleared 3/11/2025 DAVID URITA
Grading Pre-Inspection Cleared 4/25/2025 MATTHEW TORRES

Contact Information

Contractor Flexi - Tech Contracting Inc; Lic. No.: 767683-B       ,
Engineer Gaprelian,, Armen; Lic. No.: GE2668 1719 BEN LOMOND DR      GLENDALE, CA 91202
Engineer Manesh,, Behnam Abraham; Lic. No.: C38454 17337 VENTURA BLVD STE 310      ENCINO, CA 91316
Geologist Pongracz-Bartha,, Ed; Lic. No.: EG2370 7120 HAYVENHURST AVENUE, SUITE 216      VAN NUYS, CA 91406

Inspector Information

KEVIN SARGSYAN, (310) 914-3889 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Other (see comments) 7/3/2025 No Access for Inspection KENNETH NAGLE
Piling/Pier/Caisson 7/3/2025 Conditional Approval ARAM AVEDISIAN
Deputy Other (see comments) 7/7/2025 Conditional Approval KEVIN SARGSYAN
Deputy Other (see comments) 7/9/2025 Approved KEVIN SARGSYAN
Excavation/Setback/Form/Re-Bar 7/9/2025 Partial Approval KEVIN SARGSYAN
Excavation/Setback/Form/Re-Bar 8/18/2025 Partial Approval MEL KHACHATOURIAN
Deputy Other (see comments) 8/19/2025 Conditional Approval HERBERT GIRON
Excavation/Setback/Form/Re-Bar 9/11/2025 Corrections Issued KEVIN SARGSYAN
Pre-Gunite 9/11/2025 Not Ready for Inspection KEVIN SARGSYAN
Piling/Pier/Caisson 9/15/2025 Not Ready for Inspection HERBERT GIRON
Pre-Gunite 9/16/2025 Approved KEVIN SARGSYAN
Deputy Other (see comments) 9/24/2025 Conditional Approval KEVIN SARGSYAN
Gas Piping or Gas Test 1/26/2026 Corrections Issued HERBERT GIRON
Grounding or Bonding 1/26/2026 Corrections Issued HERBERT GIRON
Grounding or Bonding 2/4/2026 No Access for Inspection KEVIN SARGSYAN
Gas Piping or Gas Test 2/26/2026 Approved KEVIN SARGSYAN
Grounding or Bonding 2/26/2026 Approved KEVIN SARGSYAN
Rough-Electrical 2/26/2026 Approved KEVIN SARGSYAN
Enclosure/Fence 6/16/2026 Corrections Issued KEVIN SARGSYAN