946 N HARTZELL ST 90272
Certificate Information: 946 N HARTZELL ST 90272
- Application / Permit
- 25030-30000-03930
- Plan Check / Job No.
- B25WL05126
- Group
- Building
- Type
- Grading
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (70) Grading - Hillside
- Work Description
- *** 2025 WILDFIRE ELIGIBLE REBUILD PROJECT *** grading for new basement
- Permit Issued
- Issued on 9/2/2025
- Issuing Office
- Current Status
- Issued on 9/2/2025
Permit Application Status History
| Submitted | 6/20/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 6/24/2025 | VU NGUYEN |
| Corrections Issued | 6/30/2025 | VU NGUYEN |
| Quality Review Completed | 6/30/2025 | EUGENE BARBEAU |
| Building Plans Picked Up | 7/2/2025 | APPLICANT |
| Applicant returned to address corrections | 8/15/2025 | VU NGUYEN |
| Applicant returned to address corrections | 8/19/2025 | VU NGUYEN |
| Plan Check Approved | 8/21/2025 | VU NGUYEN |
| Plan Check Approved | 8/29/2025 | IRMA BARRAZA |
| Issued | 9/2/2025 | APPLICANT |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Architect | Walters,, Jonathan A; Lic. No.: C33220 | 4634 LAURELGROVE AVENUE STUDIO CITY, CA 91604 |
| Contractor | Zepeda Juan; Lic. No.: 1028796-B | 9525 HUNT AVE SOUTH GATE, CA 90280 |
| Engineer | Haddad,, Raymond M; Lic. No.: GE2985 | 17106 CEREDO PL GRANADA HILLS, CA 91344 |
| Engineer | Namdar,, Mansour; Lic. No.: S2976 | 16867 SEVERO PLACE ENCINO, CA 91436 |
Inspector Information
| RUSSELL BONVOULOIR, (310) 914-3899 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Initial Grading | 9/8/2025 | Partial Approval | JOHNNY MIRANDA |
| Sub-Drain | 10/8/2025 | No Access for Inspection | JOHNNY MIRANDA |
| Approved Compaction Report | 10/10/2025 | Not Ready for Inspection | JOHNNY MIRANDA |
| Bottom/Toe | 10/10/2025 | Not Ready for Inspection | JOHNNY MIRANDA |
| Sub-Drain | 10/10/2025 | Not Ready for Inspection | JOHNNY MIRANDA |
| Sub-Drain | 10/15/2025 | Partial Approval | JOHNNY MIRANDA |
| Drainage Devices/Catch Basin | 11/7/2025 | Partial Inspection | LANNY MERRICK |
| Sub-Drain | 11/7/2025 | Not Ready for Inspection | LANNY MERRICK |
| Sub-Drain | 3/10/2026 | No Access for Inspection | GERMAN RODRIGUEZ MENDOZA |
| Sub-Drain | 3/11/2026 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| Sub-Drain | 3/12/2026 | Partial Approval | RUSSELL BONVOULOIR |
| Approved Compaction Report | 4/2/2026 | Partial Inspection | GERMAN RODRIGUEZ MENDOZA |
| Bottom/Toe | 4/9/2026 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| Final | 4/9/2026 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| Rough | 4/9/2026 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| Approved Compaction Report | 4/21/2026 | Approved | LANNY MERRICK |