1647 N MALTMAN AVE 90026
Certificate Information: 1647 N MALTMAN AVE 90026
- Application / Permit
- 25030-30000-03440
- Plan Check / Job No.
- B25WL04512
- Group
- Building
- Type
- Grading
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (70) Grading - Hillside
- Work Description
- Site grading for new duplex; removal and recompaction for new ADU and site retaining walls --- 4 of 4---
- Permit Issued
- Issued on 10/10/2025
- Issuing Office
- Current Status
- Issued on 10/10/2025
Permit Application Status History
| Submitted | 5/30/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 6/19/2025 | EDWIN ESPIN |
| Corrections Issued | 6/23/2025 | EDWIN ESPIN |
| Quality Review Completed | 6/26/2025 | CHIHARU SUZUKI |
| Assigned to Zoning Architect | 6/26/2025 | KAITA SAITO |
| Building Plans Picked Up | 6/27/2025 | APPLICANT |
| Applicant returned to address corrections | 9/22/2025 | YASHAR EMAMI |
| Applicant returned to address corrections | 10/8/2025 | YASHAR EMAMI |
| Plan Check Approved | 10/10/2025 | YASHAR EMAMI |
| Issued | 10/10/2025 | APPLICANT |
Permit Application Clearance Information
| Low Impact Development (LID) | Cleared | 7/16/2025 | ERNEST TSE |
| Zoning Plan Check | Cleared | 8/26/2025 | EDEN YIGLLETU |
| GPI Written Notices | Cleared | 9/22/2025 | EDWIN ESPIN |
| Grading Pre-Inspection | Cleared | 9/22/2025 | EDWIN ESPIN |
Contact Information
| Architect | Walters,, Jonathan A; Lic. No.: C33220 | 4634 LAURELGROVE AVENUE STUDIO CITY, CA 91604 |
| Contractor | Owner-Builder | , |
| Engineer | Le,, Thang Huu; Lic. No.: S4978 | 507 MAGELLAN RD ARCADIA, CA 91007 |
| Engineer | Smith,, Melvin Bruce; Lic. No.: GE2673 | 2165 N MARVEL AVE SIMI VALLEY, CA 93065 |
Inspector Information
| RAMAZANALI ALMASI, (213) 482-0398 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Initial Grading | 10/17/2025 | Corrections Issued | RUSSELL BONVOULOIR |
| Initial Grading | 10/23/2025 | Corrections Issued | RUSSELL BONVOULOIR |
| Excavation | 10/28/2025 | Partial Approval | RUSSELL BONVOULOIR |
| Rough | 11/7/2025 | Partial Approval | RAMAZANALI ALMASI |
| Sub-Drain | 1/15/2026 | Partial Approval | RAMAZANALI ALMASI |
| Approved Compaction Report | 2/23/2026 | Approved | RAMAZANALI ALMASI |