1209 N BIENVENEDA AVE 90272
Certificate Information: 1209 N BIENVENEDA AVE 90272
- Application / Permit
- 25030-30000-02582
- Plan Check / Job No.
- B24WL08770
- Group
- Building
- Type
- Grading
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (70) Grading - Hillside
- Work Description
- **2025 Wildfire Project -- Non-Eligible Project ** Site grading for new proposed additon and retaining walls. --3 of 3 --
- Permit Issued
- Issued on 6/27/2025
- Issuing Office
- West Los Angeles
- Current Status
- Issued on 6/27/2025
Permit Application Status History
| Submitted | 11/6/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 11/21/2024 | EDWIN ESPIN |
| Corrections Issued | 12/6/2024 | EDWIN ESPIN |
| Quality Review Completed | 12/12/2024 | CHIHARU SUZUKI |
| Building Plans Picked Up | 12/27/2024 | APPLICANT |
| Applicant returned to address corrections | 4/21/2025 | EDWIN ESPIN |
| Applicant returned to address corrections | 4/24/2025 | EDWIN ESPIN |
| Plan Check Approved | 6/27/2025 | EDWIN ESPIN |
| Issued | 6/27/2025 | APPLICANT |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 4/24/2025 | EDWIN ESPIN |
| Coastal Zone | Cleared | 6/10/2025 | BRENNEN OBETO |
Contact Information
| Contractor | Milestone Builders C C S Inc; Lic. No.: 521939-B | 11916 WHITEWATER LANE MALIBU, CA 90265 |
| Engineer | Hennon,, Robert D; Lic. No.: L5573 | 601 E GLENOAKS BLVD 208 GLENDALE, CA 91207 |
| Engineer | Howe,, Carl William; Lic. No.: C44773 | 4358 SEPULVEDA BLVD CULVER CITY, CA 90230 |
| Engineer | Mahn,, Jonathan Edward; Lic. No.: C60293 | 12848 FOOTHILL BLVD SYLMAR, CA 91381 |
| Engineer | Triebold,, Mark John; Lic. No.: GE1796 | 6906 QUITO COURT CAMARILLO, CA 93012 |
| Geologist | Triebold,, Mark John; Lic. No.: GEO5692 | 6906 QUITO COURT CAMARILLO, CA 93012 |
Inspector Information
| RUSSELL BONVOULOIR, (310) 914-3899 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation | 8/20/2025 | Partial Approval | RUSSELL BONVOULOIR |
| Initial Grading | 8/20/2025 | Approved | RUSSELL BONVOULOIR |
| Rough | 8/20/2025 | Partial Approval | RUSSELL BONVOULOIR |
| Sub-Drain | 10/1/2025 | Partial Approval | JOHNNY MIRANDA |