5075 N KESTER AVE 91403
Certificate Information: 5075 N KESTER AVE 91403
- Application / Permit
- 25030-20000-02897
- Plan Check / Job No.
- B19VN17141
- Group
- Building
- Type
- Grading
- Sub-Type
- Apartment
- Primary Use
- (60) Grading - Non-Hillside
- Work Description
- GRADING R&R FOR NEW APARTMENT
- Permit Issued
- Issued on 5/16/2025
- Issuing Office
- Valley
- Current Status
- Issued on 5/16/2025
Permit Application Status History
| Submitted | 10/7/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 10/24/2019 | MARVEL DELACRUZ |
| Disabled Access Plans Picked Up | 10/25/2019 | APPLICANT |
| Corrections Issued | 11/1/2019 | MARVEL DELACRUZ |
| Green Plans Picked Up | 11/4/2019 | APPLICANT |
| Quality Review Completed | 11/5/2019 | GUANG MIN TUNG |
| Building Plans Picked Up | 11/8/2019 | APPLICANT |
| Applicant returned to address corrections | 2/28/2024 | MARVEL DELACRUZ |
| Applicant returned to address corrections | 12/18/2024 | MARVEL DELACRUZ |
| Applicant returned to address corrections | 3/14/2025 | MARVEL DELACRUZ |
| Applicant returned to address corrections | 4/29/2025 | MARVEL DELACRUZ |
| Applicant returned to address corrections | 5/13/2025 | MARVEL DELACRUZ |
| Plan Check Approved | 5/15/2025 | MARVEL DELACRUZ |
| Issued | 5/16/2025 | APPLICANT |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Sayah,, Daniel Hoshyar; Lic. No.: S6000 | 15233 VENTURA BLVD 1130 SHERMAN OAKS, CA 91403 |
Inspector Information
| MATTHEW JENKINS, (818) 374-4357 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Initial Grading | 5/21/2025 | Corrections Issued | ALEXANDER HELFER |
| Deputy Grading | 5/23/2025 | Conditional Approval | ALEXANDER HELFER |
| Initial Grading | 5/27/2025 | Corrections Issued | ALEXANDER HELFER |
| Initial Grading | 6/3/2025 | Not Ready for Inspection | ALEXANDER HELFER |
| Deputy Grading | 6/12/2025 | Approved | ALEXANDER HELFER |
| Bottom/Toe | 6/23/2025 | Partial Inspection | MANUEL TEJADA |
| Approved Compaction Report | 7/15/2025 | Approved | CHARLES POWELL |
| Bottom/Toe | 9/26/2025 | Approved | ALEXANDER HELFER |
| Final | 9/26/2025 | Not Ready for Inspection | ALEXANDER HELFER |
| Initial Grading | 9/26/2025 | Approved | ALEXANDER HELFER |
| Rough | 9/26/2025 | Not Ready for Inspection | ALEXANDER HELFER |