5614 N FULCHER AVE 91601
Certificate Information: 5614 N FULCHER AVE 91601
- Application / Permit
- 25030-20000-01457
- Plan Check / Job No.
- B25VN06409
- Group
- Building
- Type
- Grading
- Sub-Type
- Apartment
- Primary Use
- (60) Grading - Non-Hillside
- Work Description
- EPLAN****R&R Grading for New 7 story, 36 unit, apartment under Building Permit Number 22010-10000-00654 ***"Comply with Department Order effective date 09/05/2024.
- Permit Issued
- Issued on 7/30/2025
- Issuing Office
- Current Status
- Issued on 7/30/2025
Permit Application Status History
| Submitted | 3/12/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 3/27/2025 | SINA KHOSRAVI |
| Corrections Issued | 4/4/2025 | SINA KHOSRAVI |
| Quality Review Completed | 4/18/2025 | HERNAN ARREOLA |
| Applicant returned to address corrections | 6/10/2025 | SINA KHOSRAVI |
| Plan Check Approved | 6/19/2025 | SINA KHOSRAVI |
| Issued | 7/30/2025 | APPLICANT |
Permit Application Clearance Information
| Work Adjacent to Public Way | Cleared | 5/17/2025 | COLIN LOREDO |
| Eng Process Fee Ord 176,300 | Cleared | 5/21/2025 | COLIN LOREDO |
Contact Information
| Contractor | Ark Core Enterprise; Lic. No.: 1102405-B | , |
| Engineer | Smith,, Melvin Bruce; Lic. No.: GE2673 | 2165 N MARVEL AVE SIMI VALLEY, CA 93065 |
Inspector Information
| MATTHEW JENKINS, (818) 374-4357 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Initial Grading | 2/25/2026 | Approved | MATTHEW JENKINS |
| Bottom/Toe | 3/3/2026 | Conditional Approval | MATTHEW JENKINS |
| Deputy Grading | 3/3/2026 | Approved | MATTHEW JENKINS |
| Deputy Grading | 3/4/2026 | Conditional Approval | MATTHEW JENKINS |
| Deputy Grading | 3/5/2026 | Conditional Approval | MATTHEW JENKINS |
| Deputy Grading | 3/6/2026 | Conditional Approval | MATTHEW JENKINS |
| Bottom/Toe | 3/11/2026 | Partial Approval | MATTHEW JENKINS |
| Deputy Grading | 3/12/2026 | Conditional Approval | MATTHEW JENKINS |
| Deputy Grading | 3/13/2026 | Conditional Approval | MATTHEW JENKINS |
| Approved Compaction Report | 4/2/2026 | Approved | MATTHEW JENKINS |