10953 W WHIPPLE ST 91602

Certificate Information: 10953 W WHIPPLE ST 91602

Application / Permit
25030-20000-01237
Plan Check / Job No.
B25VN05184
Group
Building
Type
Grading
Sub-Type
Apartment
Primary Use
(60) Grading - Non-Hillside
Work Description
ePlan - SITE GRADING FOR PROPOSED APARTMENT UNDER 24010 10000 05221 CalOSHA permit must be obtained before construction is commenced
Permit Issued
Issued on 11/24/2025
Issuing Office
Current Status
Issued on 11/24/2025

Permit Application Status History

Submitted 2/27/2025 APPLICANT
Assigned to Plan Check Engineer 3/13/2025 STARR CHEN
Corrections Issued 3/17/2025 STARR CHEN
Quality Review Completed 3/18/2025 EUGENE BARBEAU
Plan Check Approved 11/7/2025 MANUEL MONTUFAR
Issued 11/24/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 6/25/2025 RYAN CASTRO
Eng Process Fee Ord 176,300 Cleared 6/26/2025 RYAN CASTRO
Low Impact Development (LID) Cleared 6/27/2025 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 7/8/2025 RYAN CASTRO
Trees in Parkway Cleared 7/17/2025 MIGUEL ORNELAS
Permit Cleared 7/24/2025 RYAN CASTRO

Contact Information

Architect Stockton,, Richard Kenneth; Lic. No.: C35492 20140 ZIMMERMAN PLACE      SANTA CLARITA, CA 91390
Contractor Owner-Builder       ,
Engineer Babayan,, Raffi Samuel; Lic. No.: C72168 7718 DAY STREET      LOS ANGELES, CA 91042
Engineer Berger,, Phillip Martin; Lic. No.: C13128 601 ARCADIA PL APT 203      NATIONAL CITY, CA 91950
Engineer Dejban,, Masoud; Lic. No.: S2521 17200 VENTURA BLVD STE 213A      ENCINO, CA 91316

Inspector Information

MATTHEW JENKINS, (818) 374-4357 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Initial Grading 1/27/2026 No Access for Inspection ROBERT PINA
Initial Grading 1/29/2026 Corrections Issued ROBERT PINA
Bottom/Toe 2/2/2026 Approved ALEXANDER HELFER
Deputy Grading 2/3/2026 Approved MANUEL TEJADA
Bottom/Toe 2/4/2026 Partial Approval MANUEL TEJADA
Deputy Grading 2/4/2026 Approved MANUEL TEJADA
Deputy Grading 2/5/2026 Partial Approval MANUEL TEJADA
Deputy Grading 2/6/2026 Approved ALEXANDER HELFER
Special/Order Compliance 2/6/2026 Approved ALEXANDER HELFER
Bottom/Toe 2/10/2026 Approved ROBERT PINA
Special/Order Compliance 2/12/2026 Not Ready for Inspection MATTHEW JENKINS
Bottom/Toe 2/13/2026 Partial Approval MANUEL TEJADA
Fill/Backfill 3/3/2026 Partial Inspection MATTHEW JENKINS
Approved Compaction Report 3/19/2026 Approved ALEXANDER HELFER