15272 W DE PAUW ST 90272
Certificate Information: 15272 W DE PAUW ST 90272
- Application / Permit
- 25030-10000-05144
- Plan Check / Job No.
- B25LA24410
- Group
- Building
- Type
- Grading
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (70) Grading - Hillside
- Work Description
- *2025 WILDFIRE ELIGIBLE PROJECT PER EO1**EPLAN* GRADING PERMIT FOR R&R AND SITE PREP
- Permit Issued
- Issued on 10/28/2025
- Issuing Office
- Current Status
- Issued on 10/28/2025
Permit Application Status History
| Submitted | 6/16/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 6/18/2025 | VIVIAN LAO |
| Corrections Issued | 6/24/2025 | VIVIAN LAO |
| Quality Review Completed | 6/24/2025 | JOHN FRANCIA |
| Applicant returned to address corrections | 7/15/2025 | VIVIAN LAO |
| Applicant returned to address corrections | 7/29/2025 | VIVIAN LAO |
| Applicant returned to address corrections | 8/6/2025 | VIVIAN LAO |
| Applicant returned to address corrections | 8/7/2025 | VIVIAN LAO |
| Applicant returned to address corrections | 10/8/2025 | VIVIAN LAO |
| Plan Check Approved | 10/28/2025 | VIVIAN LAO |
| Issued | 10/28/2025 | APPLICANT |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 8/8/2025 | DAVID VO |
| Excavation more than 5-ft deep | Cleared | 8/12/2025 | CALOSHA APPROVED |
| Work Adjacent to Public Way | Cleared | 10/17/2025 | JEREMY CHOK |
Contact Information
| Architect | Oreck,, Kevin Robert; Lic. No.: NA23895 | , |
| Contractor | Lannen Construction Inc; Lic. No.: 811038-B | , |
| Engineer | Jung,, Jason; Lic. No.: NA80569 | , |
Inspector Information
| RAMAZANALI ALMASI, (310) 914-3899 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Initial Grading | 10/30/2025 | Partial Approval | JOHNNY MIRANDA |
| Bottom/Toe | 11/3/2025 | Approved | LANNY MERRICK |
| Excavation | 11/5/2025 | Partial Approval | JOHNNY MIRANDA |
| Special/Order Compliance | 11/5/2025 | Not Ready for Inspection | JOHNNY MIRANDA |
| Approved Compaction Report | 12/24/2025 | Approved | RUSSELL BONVOULOIR |
| Final | 5/15/2026 | Not Ready for Inspection | LANNY MERRICK |
| Rough | 5/15/2026 | Partial Approval | LANNY MERRICK |