18600 W LANARK ST 91335
Certificate Information: 18600 W LANARK ST 91335
- Application / Permit
- 25030-10000-04750
- Plan Check / Job No.
- B25LA30608
- Group
- Building
- Type
- Grading
- Sub-Type
- Commercial
- Primary Use
- (60) Grading - Non-Hillside
- Work Description
- Grading for Installation of a new separate 1-story factory-built modular building as library/multi-purpose room on an existing charter middle school campus and associated site work per B25LA27875
- Permit Issued
- Issued on 10/13/2025
- Issuing Office
- Current Status
- Permit Finaled on 5/4/2026
Permit Application Status History
| Submitted | 8/1/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 8/5/2025 | JOE VO |
| Corrections Issued | 8/12/2025 | JOE VO |
| Plan Check Approved | 10/13/2025 | JOE VO |
| Issued | 10/13/2025 | APPLICANT |
| Permit Finaled | 5/4/2026 | ALEXANDER HELFER |
Permit Application Clearance Information
| Low Impact Development (LID) | Cleared | 9/23/2025 | MARTIN FRAGOSO |
| Eng Process Fee Ord 176,300 | Cleared | 10/1/2025 | BIAINA HARITUNIAN |
| Roof/Waste drainage to street | Cleared | 10/1/2025 | BIAINA HARITUNIAN |
Contact Information
| Architect | Tang,, Paul Reling; Lic. No.: NA24959 | , |
| Contractor | Del Amo Construction Llc; Lic. No.: 744458-B | , |
| Engineer | Thompson,, John Mark; Lic. No.: NA82557 | , |
Inspector Information
| ALEXANDER HELFER, (818) 374-4354 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Initial Grading | 10/15/2025 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| Initial Grading | 10/21/2025 | Approved | GERMAN RODRIGUEZ MENDOZA |
| SWPPP-Const. Storm Water | 10/21/2025 | Completed | GERMAN RODRIGUEZ MENDOZA |
| Bottom/Toe | 10/24/2025 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| Bottom/Toe | 10/29/2025 | Approved | ALEXANDER HELFER |
| Fill/Backfill | 11/4/2025 | Partial Inspection | GERMAN RODRIGUEZ MENDOZA |
| Approved Compaction Report | 11/13/2025 | Approved | ALEXANDER HELFER |
| Drainage Devices/Catch Basin | 1/26/2026 | Approved | ALEXANDER HELFER |
| Approved Compaction Report | 5/4/2026 | Approved | ALEXANDER HELFER |
| Final | 5/4/2026 | Permit Finaled | ALEXANDER HELFER |
| Rough | 5/4/2026 | Approved | ALEXANDER HELFER |