3751 S DELMAS TER 90034

Certificate Information: 3751 S DELMAS TER 90034

Application / Permit
25030-10000-04303
Plan Check / Job No.
B24LA32354
Group
Building
Type
Grading
Sub-Type
Apartment
Primary Use
(70) Grading - Hillside
Work Description
ePlan - SITE GRADING FOR PROPOSED APARTMENT
Permit Issued
Issued on 2/20/2026
Issuing Office
Current Status
Issued on 2/20/2026

Permit Application Status History

Submitted 11/18/2024 APPLICANT
Assigned to Plan Check Engineer 11/21/2024 MANUEL MONTUFAR
Assigned to Zoning Architect 11/21/2024 MEGAN KOLP
Corrections Issued 12/30/2024 MANUEL MONTUFAR
Quality Review Completed 12/31/2024 EUGENE BARBEAU
Plan Check Approved 2/20/2026 STARR CHEN
Issued 2/20/2026 APPLICANT

Permit Application Clearance Information

Address approval Cleared 9/29/2025 DAVID LOPEZ
Eng Process Fee Ord 176,300 Cleared 9/29/2025 DAVID LOPEZ
Low Impact Development (LID) Cleared 12/10/2025 ERNEST TSE
Roof/Waste drainage to street Cleared 12/19/2025 VLADIMIR ARUTYUNYAN
Grading Pre-Inspection Cleared 1/22/2026 STARR CHEN
Specific Plan Cleared 2/5/2026 JULISSA LOPEZ-HODOYAN

Contact Information

Contractor H T A Construction & Development; Lic. No.: 1044038-B       ,
Contractor Hta Construction & Development; Lic. No.: 1044038-B       ,
Engineer Jardine, Prouty, Kyle Addison; Lic. No.: C95048 2239 STATE AVE   UNIT B    COSTA MESA, CA 92627
Engineer Smith,, Melvin Bruce; Lic. No.: GE2673 2165 N MARVEL AVE      SIMI VALLEY, CA 93065

Inspector Information

JOHNNY MIRANDA, (310) 914-3937 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Bottom/Toe 2/25/2026 Not Ready for Inspection JESUS RODRIGUEZ
Initial Grading 2/27/2026 Partial Approval JOHNNY MIRANDA
Bottom/Toe 3/3/2026 Conditional Approval JOHNNY MIRANDA
Initial Grading 3/9/2026 No Access for Inspection JOHNNY MIRANDA
Initial Grading 3/10/2026 Not Ready for Inspection JESUS RODRIGUEZ
Bottom/Toe 3/23/2026 Partial Approval JOHNNY MIRANDA
Bottom/Toe 3/31/2026 Partial Approval JOHNNY MIRANDA
Bottom/Toe 4/3/2026 Not Ready for Inspection JOHNNY MIRANDA
Final 4/3/2026 Not Ready for Inspection JOHNNY MIRANDA
Rough 4/3/2026 Not Ready for Inspection JOHNNY MIRANDA
Fill/Backfill 4/6/2026 Not Ready for Inspection JESUS RODRIGUEZ
Approved Compaction Report 4/14/2026 Approved JESUS RODRIGUEZ
Bottom/Toe 6/9/2026 Not Ready for Inspection JESUS RODRIGUEZ