5877 W ABERNATHY DR 90045
Certificate Information: 5877 W ABERNATHY DR 90045
- Application / Permit
- 25030-10000-03079
- Plan Check / Job No.
- B25LA20156
- Group
- Building
- Type
- Grading
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (70) Grading - Hillside
- Work Description
- GRADING PERMIT FOR FOUNDATION REPAIR OF SFD, DETACHED GARAGE AND NEW RETAINING WALL CUT:64 CY FILL: 47 CY IMPORT0 CY EXPORT 17 CY "COMPLY WITH DEPARTMENT ORDER effective date 09/06/2011. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE".
- Permit Issued
- Issued on 9/18/2025
- Issuing Office
- Current Status
- Permit Finaled on 4/3/2026
Permit Application Status History
| Submitted | 5/16/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 5/22/2025 | JAD BASMA |
| Corrections Issued | 5/26/2025 | JAD BASMA |
| Quality Review Completed | 6/2/2025 | KEN GILL |
| Building Plans Picked Up | 6/27/2025 | APPLICANT |
| Plan Check Approved | 9/8/2025 | JAD BASMA |
| Issued | 9/18/2025 | APPLICANT |
| Permit Finaled | 4/2/2026 | JOHNNY MIRANDA |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 9/8/2025 | JAD BASMA |
Contact Information
| Contractor | Alpha Structural Inc; Lic. No.: 663409-B | 8334 FOOTHILL BLVD SUNLAND, CA 91040 |
Inspector Information
| JOHNNY MIRANDA, (310) 914-3937 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Initial Grading | 10/2/2025 | Approved | AL GAMBLE |
| Initial Grading | 10/7/2025 | Not Ready for Inspection | AL GAMBLE |
| Excavation | 10/24/2025 | Partial Inspection | AL GAMBLE |
| Excavation | 10/29/2025 | Not Ready for Inspection | AL GAMBLE |
| Excavation | 10/31/2025 | Approved | ROBERT PINA |
| Bottom/Toe | 11/14/2025 | Approved | LANNY MERRICK |
| Excavation | 11/14/2025 | Partial Approval | LANNY MERRICK |
| Excavation | 12/1/2025 | Partial Approval | JOHNNY MIRANDA |
| Rough | 12/16/2025 | Partial Approval | JOHNNY MIRANDA |
| Sub-Drain | 12/26/2025 | Partial Inspection | RUSSELL BONVOULOIR |
| Sub-Drain | 12/29/2025 | Partial Approval | JOHNNY MIRANDA |
| Rough | 2/9/2026 | Not Ready for Inspection | JESUS RODRIGUEZ |
| Rough | 2/23/2026 | Approved | JESUS RODRIGUEZ |
| Approved Compaction Report | 3/25/2026 | Approved | LANNY MERRICK |
| Final | 4/2/2026 | Permit Finaled | JOHNNY MIRANDA |