205 N CHAUTAUQUA BLVD 90272
Certificate Information: 205 N CHAUTAUQUA BLVD 90272
- Application / Permit
- 25030-10000-02186
- Plan Check / Job No.
- G25LA13809
- Group
- Building
- Type
- Nonbldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Retaining Wall
- Work Description
- Stabilization of southern slope using G45/2 Tecco mesh and soil nails on a 50' high slope with gradients as steep as 1.1H:1V.
- Permit Issued
- Issued on 7/1/2025
- Issuing Office
- Current Status
- Permit Finaled on 2/20/2026
Permit Application Status History
| Submitted | 4/9/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 4/10/2025 | ALAN DANG |
| Corrections Issued | 4/18/2025 | ALAN DANG |
| Quality Review Completed | 4/25/2025 | DAN RYAN EVANGELISTA |
| Applicant returned to address corrections | 5/28/2025 | ALAN DANG |
| Plan Check Approved | 5/30/2025 | ALAN DANG |
| Issued | 7/1/2025 | APPLICANT |
| Permit Finaled | 2/19/2026 | RUSSELL BONVOULOIR |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 5/28/2025 | ALAN DANG |
| Historic monument | Cleared | 5/29/2025 | RAFAEL FONTES |
| Coastal Zone | Cleared | 6/3/2025 | BRENNEN OBETO |
Contact Information
| Architect | Santa, Ana, Marcos E; Lic. No.: NA33317 | , |
| Contractor | Alloi Inc; Lic. No.: 924675-B | , |
Inspector Information
| RAMAZANALI ALMASI, (310) 914-3899 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Grading | 12/17/2025 | Conditional Approval | RUSSELL BONVOULOIR |
| Pre-Inspection | 12/17/2025 | Approved | RUSSELL BONVOULOIR |
| Deputy Grading | 12/18/2025 | Conditional Approval | JOHNNY MIRANDA |
| Deputy Grading | 1/5/2026 | Conditional Approval | RUSSELL BONVOULOIR |
| Deputy Grading | 1/8/2026 | Conditional Approval | RUSSELL BONVOULOIR |
| Deputy Grading | 1/9/2026 | Conditional Approval | RUSSELL BONVOULOIR |
| Deputy Grading | 1/12/2026 | Conditional Approval | RUSSELL BONVOULOIR |
| Deputy Grading | 1/13/2026 | Conditional Approval | RUSSELL BONVOULOIR |
| Deputy Grading | 1/14/2026 | Conditional Approval | RUSSELL BONVOULOIR |
| Deputy Grading | 1/15/2026 | Conditional Approval | RUSSELL BONVOULOIR |
| Deputy Grading | 1/16/2026 | Conditional Approval | RUSSELL BONVOULOIR |
| Pre-Inspection | 1/16/2026 | Partial Approval | RUSSELL BONVOULOIR |
| Deputy Grading | 1/20/2026 | Conditional Approval | RUSSELL BONVOULOIR |
| Deputy Grading | 1/21/2026 | Conditional Approval | RUSSELL BONVOULOIR |
| Deputy Grading | 1/22/2026 | Conditional Approval | JOHNNY MIRANDA |
| Deputy Grading | 1/23/2026 | Conditional Approval | RUSSELL BONVOULOIR |
| Deputy Grading | 2/3/2026 | Conditional Approval | RUSSELL BONVOULOIR |
| Final | 2/6/2026 | Not Ready for Inspection | RUSSELL BONVOULOIR |
| Deputy Grading | 2/9/2026 | Conditional Approval | GERMAN RODRIGUEZ MENDOZA |
| Final | 2/19/2026 | Permit Finaled | RUSSELL BONVOULOIR |