706 S HARBOR BLVD 90731
Certificate Information: 706 S HARBOR BLVD 90731
- Application / Permit
- 25030-10000-02030
- Plan Check / Job No.
- B25LA05240
- Group
- Building
- Type
- Grading
- Sub-Type
- Commercial
- Primary Use
- (60) Grading - Non-Hillside
- Work Description
- Grading permit for site preparation.
- Permit Issued
- Issued on 4/22/2025
- Issuing Office
- Current Status
- Permit Finaled on 9/25/2025
Permit Application Status History
| Submitted | 2/12/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 2/13/2025 | SALVADOR QUINTANILLA |
| Corrections Issued | 2/22/2025 | SALVADOR QUINTANILLA |
| Quality Review Completed | 2/24/2025 | PETER KIM |
| Applicant returned to address corrections | 3/26/2025 | SALVADOR QUINTANILLA |
| Applicant returned to address corrections | 4/3/2025 | SALVADOR QUINTANILLA |
| Applicant returned to address corrections | 4/7/2025 | SALVADOR QUINTANILLA |
| Applicant returned to address corrections | 4/8/2025 | SALVADOR QUINTANILLA |
| Applicant returned to address corrections | 4/17/2025 | SALVADOR QUINTANILLA |
| Plan Check Approved | 4/22/2025 | SALVADOR QUINTANILLA |
| Issued | 4/22/2025 | APPLICANT |
| Permit Finaled | 9/25/2025 | LANNY MERRICK |
Permit Application Clearance Information
| Port of LA Approval | Cleared | 4/7/2025 | MELISSA HARNE |
| ZA Case | Cleared | 4/9/2025 | MATTHEW COMPANA |
| ZA Case | Cleared | 4/9/2025 | MATTHEW COMPANA |
Contact Information
| Contractor | Elan Construction Inc; Lic. No.: 716606-B | 1503 CENTRE STREET SAN PEDRO, CA 90731 |
| Engineer | Benesh,, Michael Leroy; Lic. No.: C37893 | 404 SOUTH LIVE OAK PARK RD FALLBROOK, CA 92028 |
| Engineer | Haertle,, John Erwin; Lic. No.: GE2352 | 10744 CHURCHILL PL TUSTIN, CA 92782 |
Inspector Information
| JESUS RODRIGUEZ, (213) 216-1187 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Initial Grading | 4/28/2025 | Partial Inspection | MATTHEW JENKINS |
| Drainage Devices/Catch Basin | 5/2/2025 | Partial Inspection | MATTHEW JENKINS |
| Rough | 6/4/2025 | Corrections Issued | MATTHEW JENKINS |
| Approved Compaction Report | 9/11/2025 | Corrections Issued | MATTHEW JENKINS |
| Approved Compaction Report | 9/25/2025 | Approved | LANNY MERRICK |
| Bottom/Toe | 9/25/2025 | Approved | LANNY MERRICK |
| Final | 9/25/2025 | Permit Finaled | LANNY MERRICK |
| Rough | 9/25/2025 | Approved | LANNY MERRICK |