539 N KENMORE AVE 1-65 90004

Certificate Information: 539 N KENMORE AVE 1-65 90004

Application / Permit
25030-10000-00901
Plan Check / Job No.
B25LA05386
Group
Building
Type
Grading
Sub-Type
Apartment
Primary Use
(60) Grading - Non-Hillside
Work Description
ePlan -SITE GRADING FOR PROPOSED APARTMENT UNDER 24010-10000-04153 CalOSHA permit must be obtained before construction is commenced
Permit Issued
Issued on 12/9/2025
Issuing Office
Current Status
Issued on 12/9/2025

Permit Application Status History

Submitted 2/25/2025 APPLICANT
Assigned to Plan Check Engineer 3/13/2025 STARR CHEN
Corrections Issued 3/17/2025 STARR CHEN
Quality Review Completed 3/18/2025 EUGENE BARBEAU
Applicant returned to address corrections 8/8/2025 STARR CHEN
Plan Check Approved 12/5/2025 STARR CHEN
Issued 12/9/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 7/7/2025 DAVID LOPEZ
Eng Process Fee Ord 176,300 Cleared 7/8/2025 DAVID LOPEZ
Low Impact Development (LID) Cleared 8/5/2025 ERNEST TSE
Roof/Waste drainage to street Cleared 8/14/2025 DAVID LOPEZ

Contact Information

Architect Stockton,, Richard Kenneth; Lic. No.: NA35492       ,
Contractor Consolidated Contracting Services Inc; Lic. No.: 475813-B 181 AVENIDA LA PATA   SUITE 200    SAN CLEMENTE, CA 92673
Engineer Babayan,, Raffi Samuel; Lic. No.: C72168 7718 DAY STREET      LOS ANGELES, CA 91042
Engineer Berger,, Phillip Martin; Lic. No.: C13128 601 ARCADIA PL APT 203      NATIONAL CITY, CA 91950
Engineer Berger,, Phillip Martin; Lic. No.: NA13128       ,

Inspector Information

LANNY MERRICK, (213) 482-0398 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Initial Grading 1/12/2026 Corrections Issued RAMAZANALI ALMASI
Deputy Grading 1/20/2026 Conditional Approval RAMAZANALI ALMASI
Deputy Grading 1/21/2026 Conditional Approval RAMAZANALI ALMASI
Excavation 1/21/2026 Partial Approval RAMAZANALI ALMASI
Initial Grading 1/21/2026 Conditional Approval RAMAZANALI ALMASI
Deputy Grading 1/22/2026 Conditional Approval RAMAZANALI ALMASI
Deputy Grading 1/23/2026 Conditional Approval RAMAZANALI ALMASI
Excavation 1/23/2026 Partial Approval RAMAZANALI ALMASI
Deputy Grading 1/26/2026 Approved ROBERT PINA
Excavation 1/26/2026 Partial Approval ROBERT PINA
Excavation 1/27/2026 Partial Approval MICHAEL TEMPLE
Bottom/Toe 1/29/2026 Partial Approval RAMAZANALI ALMASI
Excavation 1/29/2026 Partial Approval RAMAZANALI ALMASI
Bottom/Toe 2/3/2026 Approved RAMAZANALI ALMASI
Excavation 2/3/2026 Approved RAMAZANALI ALMASI
Excavation 2/6/2026 Partial Approval RAMAZANALI ALMASI
Excavation 2/24/2026 Partial Approval RAMAZANALI ALMASI
Excavation 2/27/2026 Partial Approval RAMAZANALI ALMASI
Excavation 3/2/2026 Not Ready for Inspection RAMAZANALI ALMASI
Excavation 3/3/2026 Partial Approval ROBERT PINA
Excavation 3/5/2026 Partial Approval RAMAZANALI ALMASI
Drainage Devices/Catch Basin 3/18/2026 Not Ready for Inspection RAMAZANALI ALMASI
Drainage Devices/Catch Basin 3/20/2026 Approved RAMAZANALI ALMASI
Approved Compaction Report 4/20/2026 Approved RAMAZANALI ALMASI