1013 N SYCAMORE AVE 90038
Certificate Information: 1013 N SYCAMORE AVE 90038
- Application / Permit
- 25030-10000-00450
- Plan Check / Job No.
- B25LA00590
- Group
- Building
- Type
- Grading
- Sub-Type
- Commercial
- Primary Use
- (60) Grading - Non-Hillside
- Work Description
- EPLAN***PROPOSED GRADING FOR NEW OFFICE BUILDING
- Permit Issued
- Issued on 8/6/2025
- Issuing Office
- Current Status
- Issued on 8/6/2025
Permit Application Status History
| Submitted | 1/10/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 1/16/2025 | SINA KHOSRAVI |
| Corrections Issued | 1/22/2025 | SINA KHOSRAVI |
| Quality Review Completed | 1/29/2025 | GARO TELMI |
| Applicant returned to address corrections | 3/25/2025 | SINA KHOSRAVI |
| Applicant returned to address corrections | 6/12/2025 | SINA KHOSRAVI |
| Applicant returned to address corrections | 7/18/2025 | SINA KHOSRAVI |
| Plan Check Approved | 8/6/2025 | SINA KHOSRAVI |
| Issued | 8/6/2025 | APPLICANT |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 3/17/2025 | JUSTIN BICOL |
| Work Adjacent to Public Way | Cleared | 3/26/2025 | SINA KHOSRAVI |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Larocca,, Francis; Lic. No.: C75121 | 2008A BELMONT LANE REDONDO BEACH, CA 90278 |
Inspector Information
| AL GAMBLE, (213) 482-0403 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Initial Grading | 8/8/2025 | Corrections Issued | JONATHAN HOM |
| Deputy Grading | 8/11/2025 | Approved | JONATHAN HOM |
| Deputy Grading | 8/12/2025 | Approved | JONATHAN HOM |
| Bottom/Toe | 8/13/2025 | Partial Approval | JONATHAN HOM |
| Deputy Grading | 8/13/2025 | Approved | JONATHAN HOM |
| Excavation | 8/13/2025 | Partial Inspection | JONATHAN HOM |
| Approved Compaction Report | 8/25/2025 | Approved | RUSSELL BONVOULOIR |
| Special/Order Compliance | 9/8/2025 | Conditional Approval | MICHAEL TEMPLE |
| Approved Compaction Report | 1/27/2026 | Approved | MICHAEL TEMPLE |
| Sub-Drain | 3/16/2026 | Corrections Issued | AL GAMBLE |
| Sub-Drain | 3/17/2026 | Conditional Approval | RAMAZANALI ALMASI |
| Drainage Devices/Catch Basin | 3/19/2026 | Partial Approval | RAMAZANALI ALMASI |
| Fill/Backfill | 3/19/2026 | Not Ready for Inspection | AL GAMBLE |
| Sub-Drain | 3/19/2026 | Not Ready for Inspection | AL GAMBLE |
| Sub-Drain | 3/26/2026 | Not Ready for Inspection | AL GAMBLE |
| Drainage Devices/Catch Basin | 4/1/2026 | Approved | ROBERT PINA |
| Sub-Drain | 4/1/2026 | Conditional Approval | ROBERT PINA |
| Drainage Devices/Catch Basin | 4/8/2026 | Partial Approval | AL GAMBLE |
| Drainage Devices/Catch Basin | 5/22/2026 | Partial Approval | AL GAMBLE |