733 S BURLINGTON AVE 90057
Certificate Information: 733 S BURLINGTON AVE 90057
- Application / Permit
- 25030-10000-00189
- Plan Check / Job No.
- B24LA15989
- Group
- Building
- Type
- Grading
- Sub-Type
- Apartment
- Primary Use
- (60) Grading - Non-Hillside
- Work Description
- SITE GRADING, REMOVE AND RECOMPACT
- Permit Issued
- Issued on 8/22/2025
- Issuing Office
- Current Status
- Issued on 8/22/2025
Permit Application Status History
| Submitted | 8/1/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 8/8/2024 | MANUEL MONTUFAR |
| Assigned to Zoning Architect | 8/8/2024 | MEGAN KOLP |
| Corrections Issued | 8/20/2024 | MANUEL MONTUFAR |
| Quality Review Completed | 8/20/2024 | EUGENE BARBEAU |
| Plan Check Approved | 8/22/2025 | VU NGUYEN |
| Issued | 8/22/2025 | APPLICANT |
Permit Application Clearance Information
| Miscellaneous | Cleared | 5/23/2025 | DANIEL CORONADO |
| Miscellaneous | Cleared | 5/23/2025 | DANIEL CORONADO |
| Miscellaneous | Cleared | 5/23/2025 | DANIEL CORONADO |
| Historic Resource Verification | Cleared | 5/27/2025 | YASMINE BASHIRI |
| Redevelopment Project Area | Cleared | 5/27/2025 | YASMINE BASHIRI |
| Miscellaneous | Cleared | 5/28/2025 | DANIEL CORONADO |
| Work Adjacent to Public Way | Cleared | 5/30/2025 | HOK CHI CHIU |
| Low Impact Development (LID) | Cleared | 6/6/2025 | MITESH PATEL |
| Eng Process Fee Ord 176,300 | Cleared | 6/13/2025 | MICHAEL BROWN |
Contact Information
| Contractor | Labib Development Llc; Lic. No.: 1109467-B | 20904 SHELLFISH LN HUNTINGTON BEACH, CA 92648 |
| Engineer | Larocca,, Francis; Lic. No.: C75121 | 2008A BELMONT LANE REDONDO BEACH, CA 90278 |
| Engineer | Minas,, Caro Jolfaie; Lic. No.: GE601 | 4742 SAN FERNANDO RD GLENDALE, CA 91204 |
Inspector Information
| RAMAZANALI ALMASI, (213) 482-0398 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Initial Grading | 9/9/2025 | Approved | RUSSELL BONVOULOIR |
| Initial Grading | 9/11/2025 | Corrections Issued | RUSSELL BONVOULOIR |
| Bottom/Toe | 9/12/2025 | Corrections Issued | RUSSELL BONVOULOIR |
| Initial Grading | 9/13/2025 | Off-Hour Fees Due | |
| Approved Compaction Report | 9/17/2025 | Not Ready for Inspection | ROBERT PINA |
| Bottom/Toe | 9/17/2025 | Approved | ROBERT PINA |
| Final | 9/17/2025 | Corrections Issued | ROBERT PINA |
| Rough | 9/17/2025 | Approved | ROBERT PINA |
| Approved Compaction Report | 9/19/2025 | Partial Inspection | RUSSELL BONVOULOIR |
| Approved Compaction Report | 9/25/2025 | Approved | RUSSELL BONVOULOIR |
| Drainage Devices/Catch Basin | 10/21/2025 | Partial Approval | RUSSELL BONVOULOIR |
| Drainage Devices/Catch Basin | 10/22/2025 | Partial Inspection | RUSSELL BONVOULOIR |