2227 N CHISLEHURST DR 90027
Certificate Information: 2227 N CHISLEHURST DR 90027
- Application / Permit
- 25030-10000-00006
- Plan Check / Job No.
- B24LA35080
- Group
- Building
- Type
- Grading
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (70) Grading - Hillside
- Work Description
- ePlan Grading for proposed retaining wall
- Permit Issued
- Issued on 4/9/2025
- Issuing Office
- Current Status
- Permit Finaled on 2/26/2026
Permit Application Status History
| Submitted | 12/10/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 12/26/2024 | MARCELA FRANQUEZ |
| Corrections Issued | 1/2/2025 | MARCELA FRANQUEZ |
| Quality Review Completed | 1/9/2025 | TU HUA |
| Applicant returned to address corrections | 3/21/2025 | MARCELA FRANQUEZ |
| Plan Check Approved | 3/28/2025 | MARCELA FRANQUEZ |
| Issued | 4/9/2025 | APPLICANT |
| Permit Finaled | 2/26/2026 | RAMAZANALI ALMASI |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 1/2/2025 | MARCELA FRANQUEZ |
Contact Information
| Contractor | Hacienda Lopez Construction Inc; Lic. No.: 910123-B | , |
| Engineer | Baad,, Katherine Firestone; Lic. No.: C64669 | 5232 ZAKON RD TORRANCE, CA 90505 |
Inspector Information
| RAMAZANALI ALMASI, (213) 482-0398 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Initial Grading | 9/2/2025 | Approved | ROBERT PINA |
| Deputy Grading | 9/15/2025 | Conditional Approval | RUSSELL BONVOULOIR |
| Excavation | 9/16/2025 | Corrections Issued | RUSSELL BONVOULOIR |
| Bottom/Toe | 9/24/2025 | Conditional Approval | RUSSELL BONVOULOIR |
| Excavation | 9/24/2025 | Corrections Issued | RUSSELL BONVOULOIR |
| Excavation | 9/26/2025 | Partial Inspection | RUSSELL BONVOULOIR |
| Sub-Drain | 10/16/2025 | Partial Approval | RUSSELL BONVOULOIR |
| Fill/Backfill | 10/24/2025 | Partial Approval | RAMAZANALI ALMASI |
| Approved Compaction Report | 12/18/2025 | Partial Inspection | RAMAZANALI ALMASI |
| Approved Compaction Report | 2/12/2026 | Not Ready for Inspection | RAMAZANALI ALMASI |
| Approved Compaction Report | 2/13/2026 | Approved | RAMAZANALI ALMASI |
| Bottom/Toe | 2/26/2026 | Approved | RAMAZANALI ALMASI |
| Final | 2/26/2026 | Permit Finaled | RAMAZANALI ALMASI |
| Rough | 2/26/2026 | Approved | RAMAZANALI ALMASI |