20390 W ALERION PL 91364
Certificate Information: 20390 W ALERION PL 91364
- Application / Permit
- 25024-20000-00003
- Plan Check / Job No.
- B25VN13993
- Group
- Building
- Type
- Nonbldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Retaining Wall
- Work Description
- 25'-6" LENGTH WITH 6' MAX HEIGHT ADDITION TO EXTEND THE EXISTING RETAINING WALL
- Permit Issued
- Issued on 10/28/2025
- Issuing Office
- Current Status
- Permit Finaled on 4/13/2026
Permit Application Status History
| Submitted | 5/16/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 6/5/2025 | DANIEL ABRAMYAN |
| Corrections Issued | 6/12/2025 | DANIEL ABRAMYAN |
| Quality Review Completed | 6/17/2025 | OMID HEDAYAT |
| Building Plans Picked Up | 6/18/2025 | APPLICANT |
| Applicant returned to address corrections | 10/20/2025 | VAHAN JIVALAGIAN |
| Plan Check Approved | 10/28/2025 | VAHAN JIVALAGIAN |
| Issued | 10/28/2025 | APPLICANT |
| Permit Finaled | 4/10/2026 | ALEXANDER HELFER |
Permit Application Clearance Information
| Landscape for retaining wall | Cleared | 6/26/2025 | BRENNEN OBETO |
| ZA Case | Cleared | 6/26/2025 | BRENNEN OBETO |
| Roof/Waste drainage to street | Cleared | 7/1/2025 | DERRICK MAGEE |
| Eng Process Fee Ord 176,300 | Cleared | 8/14/2025 | DERRICK MAGEE |
| Grading Pre-Inspection | Cleared | 10/20/2025 | DANIEL ABRAMYAN |
Contact Information
| Contractor | Picture Build; Lic. No.: 990772-B | 12410 FOOTHILL BLVD UNIT U SYLMAR, CA 91342 |
| Engineer | Ganeshwara,, Vela; Lic. No.: GE2736 | 19420 KILFINAN ST PORTER RANCH, CA 91326 |
| Engineer | Mcpherson,, Ryan; Lic. No.: C82088 | 6169 SUNNY CIRCLE MIRA LOMA, CA 91752 |
Inspector Information
| MANUEL TEJADA, (818) 374-4339 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 11/26/2025 | Approved | ALEXANDER HELFER |
| Excavation/Setback/Form/Re-Bar | 12/10/2025 | Approved | MANUEL TEJADA |
| Excavation/Setback/Form/Re-Bar | 12/15/2025 | Partial Approval | MANUEL TEJADA |
| Masonry Wall/Backfill | 12/15/2025 | Partial Approval | MANUEL TEJADA |
| Final | 12/22/2025 | Not Ready for Inspection | MANUEL TEJADA |
| Special/Order Compliance | 12/30/2025 | Partial Approval | MANUEL TEJADA |
| Final | 1/15/2026 | Not Ready for Inspection | MANUEL TEJADA |
| Final | 2/10/2026 | Corrections Issued | MANUEL TEJADA |
| Final | 2/20/2026 | Not Ready for Inspection | MANUEL TEJADA |
| Final | 3/19/2026 | Partial Inspection | MANUEL TEJADA |
| Final | 4/10/2026 | Permit Finaled | ALEXANDER HELFER |