518 N CHAUTAUQUA BLVD 90272

Certificate Information: 518 N CHAUTAUQUA BLVD 90272

Application / Permit
25020-30000-01361
Plan Check / Job No.
B25WL05824
Group
Building
Type
Nonbldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Miscellaneous Bldg/Structure
Work Description
***2025 Eligible Wildfire Project Per Executive Order No. 1*** New detached deck over piles.
Permit Issued
Issued on 1/12/2026
Issuing Office
Current Status
Issued on 1/12/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 7/16/2025 APPLICANT
Assigned to Plan Check Engineer 7/17/2025 EDWIN ESPIN
Corrections Issued 7/22/2025 EDWIN ESPIN
Quality Review Completed 7/29/2025 CHIHARU SUZUKI
Plan Check Approved 1/12/2026 EDWIN ESPIN
Issued 1/12/2026 APPLICANT

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 7/22/2025 SAFA JAVANMARDI
Roof/Waste drainage to street Cleared 7/22/2025 SAFA JAVANMARDI
Miscellaneous Cleared 8/28/2025 DALIA MOKAYED
Miscellaneous Cleared 8/28/2025 DALIA MOKAYED
ZA Case Cleared 8/28/2025 DALIA MOKAYED
ZA Case Cleared 8/28/2025 DALIA MOKAYED
GPI Written Notices Cleared 9/29/2025 EDWIN ESPIN
Grading Pre-Inspection Cleared 9/29/2025 EDWIN ESPIN

Contact Information

Architect Noteware,, Brian Arthur; Lic. No.: C21514 845 20TH STREET, #106      SANTA MONICA, CA 90403
Contractor Owner-Builder       ,
Engineer Pasdarpour,, Mahan; Lic. No.: GE3286 22421 SHERMAN WAY   UNIT 1    WEST HILLS, CA 91307
Geologist Ruberti,, Rudolph F; Lic. No.: EG1708 6634 VALJEAN AVE      VAN NUYS, CA 91406

Inspector Information

HERBERT GIRON, (310) 914-3891 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 4/13/2026 Not Ready for Inspection DANIEL VERA
Deputy Reinf. Concrete 4/14/2026 Approved JUAN VALENZUELA
Excavation/Setback/Form/Re-Bar 4/14/2026 Partial Approval JUAN VALENZUELA
Deputy Reinf. Concrete 4/16/2026 Conditional Approval JUAN VALENZUELA
Deputy Reinf. Concrete 4/17/2026 Conditional Approval JUAN VALENZUELA
Piling/Pier/Caisson 4/29/2026 Approved HERBERT GIRON
Deputy Reinf. Concrete 5/1/2026 Conditional Approval JUAN VALENZUELA
Deputy Drilled-In Anchors 6/17/2026 Conditional Approval ANDREW NAVE
Footing/Foundation/Slab 6/29/2026 Partial Approval HERBERT GIRON
Deputy Reinf. Concrete 6/30/2026 Conditional Approval ANDREW NAVE