1201 S FIGUEROA ST 90015
Certificate Information: 1201 S FIGUEROA ST 90015
- Application / Permit
- 25020-20000-02641
- Plan Check / Job No.
- B25VN36505
- Group
- Building
- Type
- Nonbldg-New
- Sub-Type
- Commercial
- Primary Use
- (23) Shoring (Temporary)
- Work Description
- Eplan Temporary Shoring with lagging & soldier piles for Pico Hall addition of the Los Angeles Convention Center
- Permit Issued
- Issued on 2/12/2026
- Issuing Office
- Current Status
- Issued on 2/12/2026
Permit Application Status History
| Submitted | 12/18/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 12/18/2025 | GARO TELMI |
| Corrections Issued | 12/22/2025 | GARO TELMI |
| Quality Review Completed | 12/22/2025 | DANIEL CHAN |
| Applicant returned to address corrections | 2/3/2026 | GARO TELMI |
| Plan Check Approved | 2/11/2026 | GARO TELMI |
| Issued | 2/12/2026 | APPLICANT |
Permit Application Clearance Information
| City owned building/parcel | Cleared | 12/23/2025 | MASON NG |
| Abandoned oil well | Cleared | 12/31/2025 | KURT CORRAL |
| Metro Rail approval | Cleared | 1/6/2026 | GARO TELMI |
| Eng Process Fee Ord 176,300 | Cleared | 1/7/2026 | JEREMY CHOK |
| Flood clearance | Cleared | 1/22/2026 | SAMSON WONG |
| Miscellaneous | Cleared | 1/22/2026 | TERRY PHAN |
| Encroachment in public way | Cleared | 1/28/2026 | ARNULFO CHAMU |
| Work Adjacent to Public Way | Cleared | 2/3/2026 | LARRY LEE |
| Construction within easement | Cleared | 2/10/2026 | ENRIQUE ACOSTA |
| Specific Plan | Cleared | 2/10/2026 | RUBEN VASQUEZ |
| Excavation more than 5-ft deep | Cleared | 2/11/2026 | CALOSHA APPROVED |
Contact Information
| Contractor | Pcl Construction Services Inc; Lic. No.: 1055307-B | , |
| Engineer | Robinson,, Joe; Lic. No.: C96825 | 9602 NE 106TH WAY VANCOUVER, WA 98662 |
| Engineer | Tsai,, Ethan; Lic. No.: GE3004 | 1414 EAST SAMP LN PLACENTIA, CA 92870 |
Inspector Information
| DAVID BURKHEAD, (213) 482-7294 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Grading Pre-Inspection | 2/26/2026 | Not Ready for Inspection | PAUL BAZERKANIAN |
| Deputy Grading | 2/27/2026 | Partial Approval | PAUL BAZERKANIAN |
| Grading Pre-Inspection | 2/27/2026 | Partial Approval | PAUL BAZERKANIAN |
| Deputy Grading | 3/3/2026 | Conditional Approval | DAVID BURKHEAD |
| Grading Pre-Inspection | 3/3/2026 | Approved | DAVID BURKHEAD |
| Piling/Pier/Caisson | 3/4/2026 | Partial Inspection | DAVID BURKHEAD |
| Deputy Grading | 3/9/2026 | Conditional Approval | DAVID BURKHEAD |
| Deputy Grading | 3/12/2026 | Conditional Approval | DAVID BURKHEAD |
| Excavation/Setback/Form/Re-Bar | 3/12/2026 | Partial Inspection | DAVID BURKHEAD |