1444 N LACHMAN LANE 90272
Certificate Information: 1444 N LACHMAN LANE 90272
- Application / Permit
- 25020-20000-01738
- Plan Check / Job No.
- B25VN07638
- Group
- Building
- Type
- Nonbldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Shoring (Temporary)
- Work Description
- ****2025 WILDFIRE REBUILD EO8 ELIGIBLE PROJECT**** TEMPORARY SHORING FOR SFD OVER BASEMENT AND RETAINING WALL
- Permit Issued
- Issued on 1/21/2026
- Issuing Office
- Current Status
- Issued on 1/21/2026
Permit Application Status History
| Submitted | 3/20/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 3/25/2025 | RAPHAEL ROSAS |
| Assigned to Zoning Architect | 3/27/2025 | ELAHE MERRIKHI |
| Corrections Issued | 4/1/2025 | RAPHAEL ROSAS |
| Quality Review Completed | 4/1/2025 | STEVEN KIM |
| Building Plans Picked Up | 4/9/2025 | APPLICANT |
| Applicant returned to address corrections | 12/12/2025 | RAPHAEL ROSAS |
| Plan Check Approved | 1/9/2026 | RAPHAEL ROSAS |
| Issued | 1/21/2026 | APPLICANT |
Permit Application Clearance Information
| Coastal Zone | Cleared | 11/25/2025 | JULIET OH |
| ZI | Cleared | 11/25/2025 | JULIET OH |
| Grading Pre-Inspection | Cleared | 1/9/2026 | RAPHAEL ROSAS |
Contact Information
| Contractor | J L M Development; Lic. No.: 1025019-B | 1301 W 35TH PLACE LOS ANGELES, CA 90007 |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 3625 BEVERLY RIDGE DRIVE SHERMAN OAKS, CA 91423 |
| Engineer | Daugherty,, Daniel Thomas; Lic. No.: C76588 | 31129 VIA COLINAS STE 707 WESTLAKE VILLAGE, CA 91362 |
| Geologist | Byrne,, Gregory S.; Lic. No.: EG1933 | 5449 RUTHWOOD DRIVE CALABASAS, CA 91302 |
Inspector Information
| RAMAZANALI ALMASI, (310) 914-3899 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 1/26/2026 | Partial Inspection | BOBBY KEY |
| Deputy Grading | 2/27/2026 | Conditional Approval | JUAN VALENZUELA |
| Piling/Pier/Caisson | 3/18/2026 | Partial Approval | RUSSELL BONVOULOIR |
| Deputy Grading | 4/29/2026 | Conditional Approval | RUSSELL BONVOULOIR |
| Deputy Grading | 4/30/2026 | Conditional Approval | RUSSELL BONVOULOIR |
| Deputy Grading | 5/1/2026 | Conditional Approval | RUSSELL BONVOULOIR |
| Deputy Grading | 5/4/2026 | Conditional Approval | RUSSELL BONVOULOIR |
| Deputy Grading | 5/5/2026 | Conditional Approval | RUSSELL BONVOULOIR |
| Deputy Grading | 5/6/2026 | Conditional Approval | RUSSELL BONVOULOIR |
| Deputy Grading | 5/7/2026 | Conditional Approval | RUSSELL BONVOULOIR |
| Deputy Grading | 5/8/2026 | Conditional Approval | RUSSELL BONVOULOIR |
| Deputy Grading | 5/11/2026 | Conditional Approval | RUSSELL BONVOULOIR |
| Deputy Grading | 5/12/2026 | Conditional Approval | RUSSELL BONVOULOIR |
| Deputy Grading | 5/13/2026 | Conditional Approval | LANNY MERRICK |
| Deputy Grading | 5/14/2026 | Conditional Approval | RUSSELL BONVOULOIR |
| Piling/Pier/Caisson | 5/14/2026 | Partial Approval | RUSSELL BONVOULOIR |
| Deputy Grading | 5/15/2026 | Conditional Approval | RUSSELL BONVOULOIR |
| Piling/Pier/Caisson | 5/18/2026 | Partial Approval | RUSSELL BONVOULOIR |
| Piling/Pier/Caisson | 5/22/2026 | Partial Inspection | RUSSELL BONVOULOIR |
| Deputy Grading | 6/17/2026 | Conditional Approval | RUSSELL BONVOULOIR |
| Piling/Pier/Caisson | 7/9/2026 | Partial Approval | RUSSELL BONVOULOIR |
| Reinforced Concrete Frame | 7/15/2026 | Corrections Issued | LANNY MERRICK |
| Excavation/Setback/Form/Re-Bar | 7/17/2026 | Partial Approval | LANNY MERRICK |