1414 N SAN YSIDRO DR 90210

Certificate Information: 1414 N SAN YSIDRO DR 90210

Application / Permit
25020-20000-00281
Plan Check / Job No.
B25VN03932
Group
Building
Type
Nonbldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Retaining Wall
Work Description
NEW 10'-0" MAX HIGH RETAINING WALL FROM NATURAL GRADE ( 65 LF) PER ENGINEERING
Permit Issued
Issued on 3/3/2026
Issuing Office
Valley
Current Status
Permit Finaled on 7/13/2026

Permit Application Status History

Submitted 2/14/2025 APPLICANT
Assigned to Plan Check Engineer 3/6/2025 ALFRED RAMIREZ
Corrections Issued 3/12/2025 ALFRED RAMIREZ
Quality Review Completed 3/13/2025 STEVEN KIM
Building Plans Picked Up 3/18/2025 APPLICANT
Applicant returned to address corrections 5/28/2025 ALFRED RAMIREZ
Applicant returned to address corrections 9/15/2025 ALFRED RAMIREZ
Applicant returned to address corrections 9/29/2025 ALFRED RAMIREZ
Applicant returned to address corrections 1/15/2026 ALFRED RAMIREZ
Plan Check Approved 3/3/2026 ALFRED RAMIREZ
Issued 3/3/2026 APPLICANT
Permit Finaled 7/13/2026 ROBERT PINA

Permit Application Clearance Information

Landscape for retaining wall Cleared 12/8/2025 RUBEN VASQUEZ
Grading Pre-Inspection Cleared 1/15/2026 ALFRED RAMIREZ
Eng Process Fee Ord 176,300 Cleared 1/30/2026 ROSE STEIN-WENDT
Roof/Waste drainage to street Cleared 2/23/2026 JEREMY CHOK

Contact Information

Contractor Owner-Builder       ,
Engineer Sadjadi,, Abdulreza; Lic. No.: C51812 1223 WILSHIRE BLVD #169      SANTA MONICA, CA 90403

Inspector Information

ROBERT PINA, (213) 482-0404 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 3/12/2026 Approved ROBERT PINA
Pre-Inspection 4/17/2026 Approved ROBERT PINA
Piling/Pier/Caisson 5/20/2026 Approved ROBERT PINA
Deputy Reinf. Concrete 5/26/2026 Conditional Approval MICHAEL TEMPLE
Deputy Other (see comments) 6/15/2026 Approved ROBERT PINA
Reinforced Concrete Frame 6/18/2026 Approved ROBERT PINA
Deputy Shotcrete 6/23/2026 Approved ROBERT PINA
Footing/Foundation/Slab 6/23/2026 Approved ROBERT PINA
Final 7/13/2026 Permit Finaled ROBERT PINA