18825 W CALVERT ST 91335
Certificate Information: 18825 W CALVERT ST 91335
- Application / Permit
- 25020-20000-00217
- Plan Check / Job No.
- B25VN03041
- Group
- Building
- Type
- Nonbldg-New
- Sub-Type
- Commercial
- Primary Use
- (23) Miscellaneous Bldg/Structure
- Work Description
- INSTALL 10'-4" X 54' CISTERN
- Permit Issued
- Issued on 8/12/2025
- Issuing Office
- Valley
- Current Status
- Issued on 8/12/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 2/6/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 2/13/2025 | RAPHAEL ROSAS |
| Corrections Issued | 2/18/2025 | RAPHAEL ROSAS |
| Quality Review Completed | 2/18/2025 | STEVEN KIM |
| Building Plans Picked Up | 2/20/2025 | APPLICANT |
| Applicant returned to address corrections | 6/5/2025 | RAPHAEL ROSAS |
| Applicant returned to address corrections | 7/11/2025 | RAPHAEL ROSAS |
| Plan Check Approved | 8/12/2025 | RAPHAEL ROSAS |
| Issued | 8/12/2025 | APPLICANT |
Permit Application Clearance Information
| ZA Case | Cleared | 6/20/2025 | MAYELA VILLA |
| Excavation more than 5-ft deep | Cleared | 8/12/2025 | CALOSHA APPROVED |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Naim,, Soleiman Israel; Lic. No.: S2454 | 403 21ST ST SANTA MONICA, CA 90402 |
| Engineer | Smith,, Melvin Bruce; Lic. No.: GE2673 | 2165 N MARVEL AVE SIMI VALLEY, CA 93065 |
Inspector Information
| BRIAN KELLY, (818) 374-1127 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 8/29/2025 | Not Ready for Inspection | BRIAN KELLY |
| Reinforced Concrete Frame | 9/2/2025 | Conditional Approval | FARHAD DADBIN |
| Deputy Reinf. Concrete | 9/3/2025 | Conditional Approval | JEFFREY DURAN |
| Deputy Reinf. Concrete | 10/14/2025 | Conditional Approval | BRIAN KELLY |
| Deputy Reinf. Concrete | 10/17/2025 | Conditional Approval | BRIAN KELLY |
| Reinforced Concrete Frame | 11/13/2025 | Partial Approval | BRIAN KELLY |
| Deputy Reinf. Concrete | 11/14/2025 | Conditional Approval | BRIAN KELLY |