2101 E PACIFIC COAST HWY 90744

Certificate Information: 2101 E PACIFIC COAST HWY 90744

Application / Permit
25020-10000-02376
Plan Check / Job No.
B25LA47621
Group
Building
Type
Nonbldg-New
Sub-Type
Commercial
Primary Use
(23) Miscellaneous Bldg/Structure
Work Description
New Structural System to Support Platform and new Piping for HCU Lopa Project
Permit Issued
Issued on 5/20/2026
Issuing Office
Current Status
CofO Issued on 7/16/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/14/2025 APPLICANT
Assigned to Zoning Architect 11/20/2025 DAVID ZHENG
Assigned to Plan Check Engineer 11/25/2025 SERGIO GUTIERREZ
Corrections Issued 12/3/2025 SERGIO GUTIERREZ
Quality Review Completed 12/3/2025 PRANITA SHAH
Applicant returned to address corrections 3/3/2026 SERGIO GUTIERREZ
Plan Check Approved 5/19/2026 SERGIO GUTIERREZ
Issued 5/20/2026 APPLICANT
Permit Finaled 7/16/2026 DAVID TSAU
CofO Issued 7/16/2026 DAVID TSAU
Permit Finaled 7/16/2026 DAVID TSAU

Permit Application Clearance Information

Zoning Plan Check Cleared 1/5/2026 Jesse Arellano
Abandoned oil well Cleared 5/11/2026 RUEL COLE

Contact Information

Contractor Schultz Industrial Services Inc; Lic. No.: 685876-A 777 N ELDRIDGE PARKWAY STE 900      HOUSTON, TX 77079
Engineer Fadaeian,, Ramin; Lic. No.: NA6338       ,
Engineer Lay,, Chi-Hung Garry; Lic. No.: GE508 885 S ORANGE GROVE BLVD APT 39      PASADENA, CA 91105

Inspector Information

MICHAEL PETRUSKO, (310) 732-4552 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 5/29/2026 Not Ready for Inspection MICHAEL PETRUSKO
Pre-Inspection 5/29/2026 Not Ready for Inspection MICHAEL PETRUSKO
Excavation/Setback/Form/Re-Bar 6/1/2026 Partial Inspection DAVID TSAU
Piling/Pier/Caisson 6/1/2026 Partial Inspection DAVID TSAU
Pre-Inspection 6/1/2026 Partial Inspection DAVID TSAU
Deputy Reinf. Concrete 6/2/2026 Conditional Approval MICHAEL PETRUSKO
Excavation/Setback/Form/Re-Bar 6/2/2026 Not Ready for Inspection DAVID TSAU
Pre-Inspection 6/2/2026 Not Ready for Inspection DAVID TSAU
Deputy Reinf. Concrete 6/3/2026 Partial Approval DAVID TSAU
Footing/Foundation/Slab 6/3/2026 Partial Approval DAVID TSAU
Deputy Reinf. Concrete 6/4/2026 Conditional Approval DAVID TSAU
Deputy Reinf. Concrete 6/9/2026 Conditional Approval MICHAEL PETRUSKO
Excavation/Setback/Form/Re-Bar 6/9/2026 Approved MICHAEL PETRUSKO
Pre-Inspection 6/9/2026 Approved MICHAEL PETRUSKO
Deputy Steel/Welding 6/15/2026 Conditional Approval MICHAEL PETRUSKO
Deputy Steel/Welding 6/16/2026 Conditional Approval MICHAEL PETRUSKO
Deputy Steel/Welding 6/17/2026 Conditional Approval MICHAEL PETRUSKO
Deputy Steel/Welding 6/18/2026 Conditional Approval MICHAEL PETRUSKO
Deputy Reinf. Concrete 6/23/2026 Conditional Approval MICHAEL PETRUSKO
Final 7/7/2026 Conditional Approval MICHAEL PETRUSKO
Reinforced Concrete Frame 7/7/2026 Approved MICHAEL PETRUSKO
Structural Steel Frame 7/7/2026 Approved MICHAEL PETRUSKO