841 N JACON WAY 90272
Certificate Information: 841 N JACON WAY 90272
- Application / Permit
- 25020-10000-02234
- Plan Check / Job No.
- B25LA41244
- Group
- Building
- Type
- Nonbldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Retaining Wall
- Work Description
- Eplan ****2025 Wildfire*** FIRE-REBUILD PER EO#1 new site retaining walls
- Permit Issued
- Issued on 1/12/2026
- Issuing Office
- Current Status
- Issued on 1/12/2026
Permit Application Status History
| Submitted | 10/2/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 10/8/2025 | SERGIO SILVA |
| Corrections Issued | 10/12/2025 | JAD BASMA |
| Quality Review Completed | 10/20/2025 | HERNAN ARREOLA |
| Plan Check Approved | 1/5/2026 | SERGIO SILVA |
| No Progress | 1/6/2026 | SERGIO SILVA |
| Plan Check Approved | 1/6/2026 | SERGIO SILVA |
| No Progress | 1/8/2026 | SERGIO SILVA |
| Plan Check Approved | 1/8/2026 | SERGIO SILVA |
| Issued | 1/12/2026 | APPLICANT |
Permit Application Clearance Information
| Landscape for retaining wall | Cleared | 12/2/2025 | DALIA MOKAYED |
| Excavation more than 5-ft deep | Cleared | 1/5/2026 | CALOSHA APPROVED |
Contact Information
| Architect | , ; Lic. No.: C34496 | , |
| Contractor | Drexel Construction Management Llc; Lic. No.: 1014160-B | 5166 W PICO BLVD LOS ANGELES, CA 90019 |
| Engineer | Barajas,, George; Lic. No.: L8399 | 3635 SHADOW GROVE RD PASADENA, CA 91107 |
| Engineer | Bayani-Rad,, Padra; Lic. No.: C86320 | 15901 HAWTHORNE BLVD UNIT 220 LAWNDALE, CA 90260 |
| Engineer | Obando,, Gaspar Eduardo; Lic. No.: C71382 | 3101 OCEAN PARK BLVD STE 100, PMB 122 SANTA MONICA, CA 90405 |
| Engineer | Tucker,, Keith D; Lic. No.: GE841 | PO BOX 8133 HUNTINGTON BEACH, CA 92615 |
Inspector Information
| RUSSELL BONVOULOIR, (310) 914-3899 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 2/12/2026 | Partial Inspection | RUSSELL BONVOULOIR |
| Excavation/Setback/Form/Re-Bar | 2/27/2026 | Partial Approval | RUSSELL BONVOULOIR |
| Footing/Foundation/Slab | 3/11/2026 | Partial Approval | RUSSELL BONVOULOIR |
| Excavation/Setback/Form/Re-Bar | 3/18/2026 | Partial Approval | RUSSELL BONVOULOIR |
| Footing/Foundation/Slab | 3/31/2026 | Partial Approval | RUSSELL BONVOULOIR |
| Footing/Foundation/Slab | 4/2/2026 | Partial Approval | RUSSELL BONVOULOIR |
| Footing/Foundation/Slab | 5/4/2026 | Partial Inspection | RUSSELL BONVOULOIR |