1119 N SANBORN AVE 90029
Certificate Information: 1119 N SANBORN AVE 90029
- Application / Permit
- 25020-10000-01657
- Plan Check / Job No.
- B25LA33844
- Group
- Building
- Type
- Nonbldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Fence Wall
- Work Description
- NEW BLOCK WALL PER STANDARD PLAN # 520 AND 2 NEW RETAINING WALLS PER FIGURE 2 OF INFORMATION BULLETINP/BC 2023-002
- Permit Issued
- Issued on 9/23/2025
- Issuing Office
- Metro
- Current Status
- Permit Finaled on 5/22/2026
Permit Application Status History
| Submitted | 8/14/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 8/14/2025 | CARLOS MONTES |
| Corrections Issued | 8/14/2025 | CARLOS MONTES |
| Plan Check Approved | 9/23/2025 | CARLOS MONTES |
| Issued | 9/23/2025 | APPLICANT |
| Permit Finaled | 5/22/2026 | RAMAZANALI ALMASI |
Permit Application Clearance Information
| Miscellaneous | Cleared | 8/26/2025 | JACQUELINE TORRES |
| Grading Pre-Inspection | Cleared | 9/23/2025 | CARLOS MONTES |
Contact Information
| Contractor | Jburton Inc; Lic. No.: 981184-B | 1976 S LA CIENEGA BOULEVARD STE 292 LOS ANGELES, CA 90034 |
Inspector Information
| RAMAZANALI ALMASI, (213) 482-0398 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Masonry Wall/Backfill | 12/23/2025 | Corrections Issued | RAMAZANALI ALMASI |
| Excavation/Setback/Form/Re-Bar | 12/30/2025 | Partial Approval | RAMAZANALI ALMASI |
| Grading Pre-Inspection | 12/30/2025 | Approved | RAMAZANALI ALMASI |
| Final | 1/13/2026 | Partial Approval | RAMAZANALI ALMASI |
| Excavation/Setback/Form/Re-Bar | 3/9/2026 | Partial Approval | RAMAZANALI ALMASI |
| Footing/Foundation/Slab | 3/9/2026 | Partial Approval | RAMAZANALI ALMASI |
| Masonry Wall/Backfill | 3/9/2026 | Partial Approval | RAMAZANALI ALMASI |
| Masonry Wall/Backfill | 3/18/2026 | Partial Approval | RAMAZANALI ALMASI |
| Masonry Wall/Backfill | 3/25/2026 | Partial Approval | RAMAZANALI ALMASI |
| Footing/Foundation/Slab | 5/1/2026 | Partial Inspection | RAMAZANALI ALMASI |
| Excavation/Setback/Form/Re-Bar | 5/6/2026 | Partial Inspection | RAMAZANALI ALMASI |
| Final | 5/22/2026 | Permit Finaled | RAMAZANALI ALMASI |