16200 W MULHOLLAND DR 90049

Certificate Information: 16200 W MULHOLLAND DR 90049

Application / Permit
25020-10000-01517
Plan Check / Job No.
B25LA32165
Group
Building
Type
Nonbldg-New
Sub-Type
Commercial
Primary Use
(61) Use of Land
Work Description
**2025 Wildfire Project. Non-Eligible Fire Rebuild.** **USE OF LAND FOR IRREGULAR-SHAPED 67' X 63'-8" ( 3800 SQ.FT.) PLAY PLACE IN A SCHOOL.
Permit Issued
Issued on 12/3/2025
Issuing Office
Metro
Current Status
CofO Issued on 4/28/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/4/2025 APPLICANT
Assigned to Plan Check Engineer 8/7/2025 JOHNNY WU
Assigned to Zoning Architect 8/14/2025 JOHNNY WU
Corrections Issued 8/14/2025 JOHNNY WU
Building Plans Picked Up 8/15/2025 APPLICANT
Quality Review Completed 8/25/2025 KEN GILL
Applicant returned to address corrections 9/25/2025 JOHNNY WU
Applicant returned to address corrections 10/29/2025 JOHNNY WU
Plan Check Approved 12/3/2025 JOHNNY WU
Issued 12/3/2025 APPLICANT
Permit Finaled 4/28/2026 VASIL MIHALEV
CofO Issued 4/28/2026 VASIL MIHALEV
Permit Finaled 4/28/2026 VASIL MIHALEV

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 8/14/2025 CINDY QI
Roof/Waste drainage to street Cleared 8/14/2025 CINDY QI
Tract Map conditions Cleared 9/10/2025 DALIA MOKAYED
ZA Case Cleared 9/10/2025 DALIA MOKAYED
ZA Case Cleared 9/10/2025 DALIA MOKAYED
ZA Case Cleared 9/10/2025 DALIA MOKAYED
Grading Pre-Inspection Cleared 9/11/2025 LANNY MERRICK
ZA Case Cleared 9/15/2025 DALIA MOKAYED
ZA Case Cleared 9/15/2025 DALIA MOKAYED
ZA Case Cleared 9/15/2025 DALIA MOKAYED
ZA Case Cleared 9/15/2025 DALIA MOKAYED
DAS Clearance Cleared 10/3/2025 JOHNNY WU
Specific Plan Cleared 11/13/2025 TIFFANY CORRALES

Contact Information

Contractor Z R Built Homes; Lic. No.: 915306-B 6094 NELDA ST      SIMI VALLEY, CA 93063
Landscape Architect Compton,, Allen Ayres; Lic. No.: LA5565 448 S HILL STREET      LOS ANGELES, CA 90013

Inspector Information

ROGELIO REYNA, (310) 914-3920 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 1/20/2026 Partial Approval FARHAD DADBIN
Final 1/23/2026 Corrections Issued CASIMIR BRITTON
Excavation/Setback/Form/Re-Bar 2/2/2026 Not Ready for Inspection PAUL DAVIDSON
Footing/Foundation/Slab 2/9/2026 Partial Approval ROGELIO REYNA
Final 2/25/2026 Partial Approval ROGELIO REYNA