8730 W ALDEN DR 90048
Certificate Information: 8730 W ALDEN DR 90048
- Application / Permit
- 25020-10000-01477
- Plan Check / Job No.
- B25LA31588
- Group
- Building
- Type
- Nonbldg-New
- Sub-Type
- Commercial
- Primary Use
- (23) Shoring (Temporary)
- Work Description
- TEMPORARY SHORING WITH LAGGING & SOLDIER PILES FOR A NEW 10-STORY RESEARCH BUILDING. ( UNDER BUILDING PERMIT # 24010-10000-03819)
- Permit Issued
- Issued on 12/2/2025
- Issuing Office
- Metro
- Current Status
- Issued on 12/2/2025
Permit Application Status History
| Submitted | 7/31/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 8/6/2025 | GARO TELMI |
| Corrections Issued | 8/14/2025 | GARO TELMI |
| Quality Review Completed | 8/14/2025 | KEN GILL |
| Building Plans Picked Up | 8/15/2025 | APPLICANT |
| Plan Check Approved | 12/2/2025 | GARO TELMI |
| Issued | 12/2/2025 | APPLICANT |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 9/2/2025 | WALLIE JONG |
| "D" conditions | Cleared | 9/10/2025 | JASON CHAN |
| "Q" conditions | Cleared | 9/10/2025 | JASON CHAN |
| "T" removal | Cleared | 9/10/2025 | JASON CHAN |
| CPC | Cleared | 9/10/2025 | JASON CHAN |
| CPC | Cleared | 9/10/2025 | JASON CHAN |
| ZA Case | Cleared | 9/10/2025 | JASON CHAN |
| ZI | Cleared | 9/10/2025 | JASON CHAN |
| Abandoned oil well | Cleared | 10/2/2025 | JOHN CONNEALLY |
| Work Adjacent to Public Way | Cleared | 11/4/2025 | LARRY LEE |
| Excavation more than 5-ft deep | Cleared | 11/6/2025 | CALOSHA APPROVED |
Contact Information
| Contractor | Rudolph & Sletten Inc; Lic. No.: 198069-B | 120 CONSTITUTION DRIVE MENLO PARK, CA 94025 |
| Engineer | Murphy,, Mark Andrew; Lic. No.: GE2777 | 24685 VIA BUENA SUERTE YORBA LINDA, CA 92887 |
| Engineer | Robinson,, Joe; Lic. No.: C96825 | 9602 NE 106TH WAY VANCOUVER, WA 98662 |
Inspector Information
| IAN BLINN, (213) 482-7361 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRISTOPHER BLACKWOOD, (213) 482-7361 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Grading | 1/15/2026 | Partial Approval | MARTIN TAVITIAN |
| Deputy Grading | 2/2/2026 | Partial Approval | IAN BLINN |
| Pre-Inspection | 3/6/2026 | Not Ready for Inspection | CHRISTOPHER BLACKWOOD |