5220 W SANCHEZ DR 90008

Certificate Information: 5220 W SANCHEZ DR 90008

Application / Permit
25020-10000-01045
Plan Check / Job No.
B25LA23292
Group
Building
Type
Nonbldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Retaining Wall
Work Description
Eplan. New retaining wall (rear of property)
Permit Issued
Issued on 8/13/2025
Issuing Office
Current Status
Issued on 8/13/2025

Permit Application Status History

Submitted 6/4/2025 APPLICANT
Assigned to Plan Check Engineer 6/18/2025 KHEDER ALRAZAA
Corrections Issued 6/26/2025 KHEDER ALRAZAA
Quality Review Completed 7/7/2025 GARO TELMI
Applicant returned to address corrections 7/29/2025 KHEDER ALRAZAA
Applicant returned to address corrections 8/1/2025 KHEDER ALRAZAA
Plan Check Approved 8/13/2025 KHEDER ALRAZAA
Issued 8/13/2025 APPLICANT

Permit Application Clearance Information

Excavation more than 5-ft deep Cleared 8/1/2025 CALOSHA APPROVED
Grading Pre-Inspection Cleared 8/1/2025 KHEDER ALRAZAA
Landscape for retaining wall Cleared 8/11/2025 DANIEL CORONADO

Contact Information

Contractor Amb Floor & Design Inc; Lic. No.: 1020606-B       ,
Contractor Amb Floor Design; Lic. No.: 1020606-B       ,
Engineer Banaie,, Saeed; Lic. No.: C32792 6732 WHITE OAK AVE      VAN NUYS, CA 91406
Engineer Salehipour,, Sassan A; Lic. No.: C44172 1290 NORTH LAKE AVENUE STE 204      PASADENA, CA 91104
Engineer Salehipour,, Sassan A; Lic. No.: GE2579 1290 N LAKE AVENUE #204      PASADENA, CA 91104

Inspector Information

AL GAMBLE, (213) 482-0403 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Grading Pre-Inspection 8/15/2025 Not Ready for Inspection LUIS CASTRO
Pre-Inspection 8/15/2025 Not Ready for Inspection LUIS CASTRO
Piling/Pier/Caisson 8/21/2025 Partial Approval JONATHAN HOM
Deputy Reinf. Concrete 8/22/2025 Approved JONATHAN HOM
Piling/Pier/Caisson 8/28/2025 Not Ready for Inspection JONATHAN HOM
Piling/Pier/Caisson 8/29/2025 Partial Inspection JONATHAN HOM
Deputy Reinf. Concrete 9/2/2025 Approved JONATHAN HOM
Footing/Foundation/Slab 9/18/2025 Approved ROBERT PINA
Deputy Reinf. Concrete 9/19/2025 Approved JONATHAN HOM
Deputy Reinf. Concrete 10/6/2025 Approved ROBERT PINA
Reinforced Concrete Frame 10/6/2025 Conditional Approval ROBERT PINA
Deputy Shotcrete 10/7/2025 Conditional Approval RUSSELL BONVOULOIR