1907 S ARLINGTON AVE 90018

Certificate Information: 1907 S ARLINGTON AVE 90018

Application / Permit
25020-10000-00993
Plan Check / Job No.
B25LA22265
Group
Building
Type
Nonbldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(23) Shoring (Permanent)
Work Description
ePlan: Proposed shoring to remove and replace under ground fueling tanks within the existing gas station. 1 OF 2
Permit Issued
Issued on 11/25/2025
Issuing Office
Current Status
Issued on 11/25/2025

Permit Application Status History

Submitted 5/30/2025 APPLICANT
Assigned to Zoning Architect 6/12/2025 AMIR NAKHLA
Assigned to Plan Check Engineer 6/18/2025 MICHAEL LOPEZ
Corrections Issued 7/3/2025 MICHAEL LOPEZ
Quality Review Completed 7/3/2025 PRANITA SHAH
Plan Check Approved 10/28/2025 MICHAEL LOPEZ
No Progress 11/12/2025 MICHAEL LOPEZ
Plan Check Approved 11/12/2025 MICHAEL LOPEZ
Issued 11/25/2025 APPLICANT

Permit Application Clearance Information

Zoning Plan Check Cleared 6/16/2025 Shangqin Xie
Work Adjacent to Public Way Cleared 7/5/2025 LARRY LEE
Eng Process Fee Ord 176,300 Cleared 7/14/2025 JESSICA OPINION

Contact Information

Contractor Progressive Fueling Construction Inc; Lic. No.: 894043-A 936 E NOCTA STREET      ONTARIO, CA 91764
Engineer Mirzadeh,, Amir; Lic. No.: C58119 P O BOX 572110      TARZANA, CA 91357
Engineer Oconnor,, Scott; Lic. No.: C85366 5540 E VISTA DEL RIO      ANAHEIM, CA 92807
Geologist Rahimikian,, Pedram; Lic. No.: EG2683 20335 VENTURA BLVD   SUITE 103    WOODLAND HILLS, CA 91364

Inspector Information

IAN BLINN, (213) 482-7361 Office Hours: 7:00-8:00 AM MON-FRI
CHRISTOPHER BLACKWOOD, (213) 482-7361 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Final 1/28/2026 Partial Approval IAN BLINN
Rough 3/19/2026 Partial Approval PAUL BAZERKANIAN