5312 N RADFORD AVE 91607
Certificate Information: 5312 N RADFORD AVE 91607
- Application / Permit
- 25016-90000-34703
- Plan Check / Job No.
- --
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- Re-roof with Class A or B roof covering material weighing less than 6 pounds per sq. ft. over new solid sheathing 15 Squares. Class A roof covering is required within Very High Fire Hazard Severity Zone (VHFHSZ). For residential roof replacement > 50% of the total roof area, apply Cool Roof Product labeled and certified by Cool Roof Rating Council (CRRC). Cool Roof may be required for non-residential buildings per Title 24, Part 6, Section 141.0(b)2B. Fire damage repair for residential buildings only (maximum 10% of replacement cost of building).
- Permit Issued
- Issued on 11/24/2025
- Issuing Office
- Current Status
- Issued on 11/24/2025
Permit Application Status History
| Issued | 11/24/2025 | INTERNET PERMIT |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | West End Construction Corp; Lic. No.: 1139898-B | 8730 CHARLEVILLE BLVD #203 BEVERLY HILLS, CA 90211 |
Inspector Information
| JEFFREY FULTON, (818) 374-1132 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| Final | 7/10/2026 |
Inspection Request History
| Final | 1/21/2026 | Conditional Approval | RAFAEL CORTES |
| Wood Frame | 1/28/2026 | Not Ready for Inspection | JEFFREY FULTON |
| Wood Frame | 1/30/2026 | Partial Inspection | JEFFREY FULTON |
| Wood Frame | 2/4/2026 | Not Ready for Inspection | JEFFREY FULTON |
| Wood Frame | 2/5/2026 | Partial Inspection | JEFFREY FULTON |
| Insulation | 2/9/2026 | Partial Inspection | JEFFREY FULTON |
| Interior/Exterior Lathing | 2/10/2026 | Partial Inspection | JEFFREY FULTON |
| Wood Frame | 2/10/2026 | Corrections Issued | JEFFREY FULTON |
| Insulation | 2/12/2026 | Partial Approval | EDWIN GREGORYONA |
| Drywall Nailing | 2/13/2026 | Approved | SEAN GRIFFITH |
| Drywall Nailing | 2/18/2026 | Partial Approval | EDWIN GREGORYONA |
| Interior/Exterior Lathing | 3/2/2026 | Partial Approval | SEAN GRIFFITH |
| Interior/Exterior Lathing | 3/9/2026 | Partial Inspection | ANDREW DORSO |
| Final | 7/2/2026 | No Access for Inspection | DEANDRE HOFFMAN |