2461 N MCCREADY AVE 90039

Certificate Information: 2461 N MCCREADY AVE 90039

Application / Permit
25016-90000-32093
Plan Check / Job No.
--
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
Re-roof with Class A or B roof covering material weighing less than 6 pounds per sq. ft. over existing solid sheathing 21 Squares. Class A roof covering is required within Very High Fire Hazard Severity Zone (VHFHSZ). For residential roof replacement > 50% of the total roof area, apply Cool Roof Product labeled and certified by Cool Roof Rating Council (CRRC). Cool Roof may be required for non-residential buildings per Title 24, Part 6, Section 141.0(b)2B. 3 bathroom(s).Bathroom remodel for residential buildings (no structural changes). Replace drywall (no new walls added) for single family dwellings and duplexes only. Kitchen remodel for residential buildings (no structural changes).
Permit Issued
Issued on 10/27/2025
Issuing Office
Current Status
Issued on 10/27/2025

Permit Application Status History

Issued 10/27/2025 INTERNET PERMIT

Permit Application Clearance Information

No Data Available.

Contact Information

Contractor Owner-Builder       ,

Inspector Information

HAMIK HARTOUNIAN, (213) 202-3275 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Floor/Roof Diaphrgm/Shear Wall 10/30/2025 Partial Approval BRENDAN MORELLI
Final 11/14/2025 Not Ready for Inspection HAMIK HARTOUNIAN
PLUMBING-Rough 11/14/2025 Corrections Issued HAMIK HARTOUNIAN
Sewer 11/14/2025 Not Ready for Inspection HAMIK HARTOUNIAN
ELECTRICAL-Rough 11/18/2025 Corrections Issued HAMIK HARTOUNIAN
PLUMBING-Rough 11/18/2025 Partial Approval HAMIK HARTOUNIAN
Sewer 11/18/2025 Not Ready for Inspection HAMIK HARTOUNIAN
ELECTRICAL-Rough 12/2/2025 Approved HAMIK HARTOUNIAN
HVAC-Rough 12/4/2025 Not Ready for Inspection HAMIK HARTOUNIAN
Interior/Exterior Lathing 12/4/2025 Partial Approval HAMIK HARTOUNIAN
Insulation 12/6/2025 Partial Approval KEVIN SARGSYAN
Drywall Nailing 12/13/2025 Partial Approval JEFFREY HARTLINE
HVAC-Rough 12/13/2025 Partial Approval JEFFREY HARTLINE
Interior/Exterior Lathing 12/13/2025 Partial Approval JEFFREY HARTLINE
ELECTRICAL-Final 5/20/2026 Corrections Issued ROY SPAULDING
Final 5/20/2026 Corrections Issued ROY SPAULDING
HVAC-Final 5/20/2026 Not Ready for Inspection ROY SPAULDING
PLUMBING-Final 5/20/2026 Not Ready for Inspection ROY SPAULDING
Special/Order Compliance 5/20/2026 Partial Inspection BRIAN SULLIVAN
ELECTRICAL-Final 5/26/2026 Approved HAMIK HARTOUNIAN
Final 5/26/2026 Corrections Issued HAMIK HARTOUNIAN
HVAC-Final 5/26/2026 Corrections Issued HAMIK HARTOUNIAN
PLUMBING-Final 5/26/2026 Approved HAMIK HARTOUNIAN
ELECTRICAL-Final 5/29/2026 Approved HAMIK HARTOUNIAN
Final 5/29/2026 Corrections Issued HAMIK HARTOUNIAN
HVAC-Final 5/29/2026 Approved HAMIK HARTOUNIAN
PLUMBING-Final 5/29/2026 Approved HAMIK HARTOUNIAN