1640 E 110TH ST 90059
Certificate Information: 1640 E 110TH ST 90059
- Application / Permit
- 25016-70000-30632
- Plan Check / Job No.
- B25SL01167
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Convert attached garage (242sf) and porch (156sf) to habitable space for dwellig. Create two additional bedrooms and bathroom.
- Permit Issued
- Issued on 12/23/2025
- Issuing Office
- South Los Angeles
- Current Status
- CofO in Progress on 3/10/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 10/14/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 10/21/2025 | RICARDO RAMIREZ |
| Corrections Issued | 10/21/2025 | RICARDO RAMIREZ |
| Applicant returned to address corrections | 10/28/2025 | RICARDO RAMIREZ |
| Plan Check Approved | 12/23/2025 | RICARDO RAMIREZ |
| Issued | 12/23/2025 | APPLICANT |
| CofO in Progress | 3/10/2026 | ARTHUR NEGRETE |
| CofO in Progress | 4/6/2026 | ARTHUR NEGRETE |
| CofO in Progress | 4/14/2026 | ARTHUR NEGRETE |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 11/7/2025 | CELINA MORENO |
| Sewer availability | Cleared | 11/24/2025 | JEREMY CHOK |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOHN KLARIN, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARTHUR NEGRETE, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 1/13/2026 | Approved | ARTHUR NEGRETE |
| BUILDING-Rough-Frame | 1/27/2026 | Approved | ARTHUR NEGRETE |
| Excavation/Setback/Form/Re-Bar | 1/27/2026 | Approved | ARTHUR NEGRETE |
| Green Building Rough | 1/27/2026 | Approved | ARTHUR NEGRETE |
| Insulation | 1/27/2026 | Corrections Issued | ARTHUR NEGRETE |
| Interior/Exterior Lathing | 1/27/2026 | Approved | ARTHUR NEGRETE |
| Drywall Nailing | 1/30/2026 | Approved | ARTHUR NEGRETE |
| Insulation | 1/30/2026 | Approved | ARTHUR NEGRETE |
| Final | 2/3/2026 | Corrections Issued | ARTHUR NEGRETE |
| Green Building Final | 2/3/2026 | Approved | ARTHUR NEGRETE |
| SGSOV-Seismic Gas S/O Valve | 2/3/2026 | SGSOV Approved | ARTHUR NEGRETE |
| Service/Power Release | 2/3/2026 | Not Required | ARTHUR NEGRETE |
| Smoke Detectors | 2/3/2026 | Approved | ARTHUR NEGRETE |
| PLUMBING-Final | 2/9/2026 | Corrections Issued | ARTHUR NEGRETE |
| Final | 3/2/2026 | Partial Approval | ARTHUR NEGRETE |
| ELECTRICAL-Final | 3/9/2026 | Approved | ARTHUR NEGRETE |
| Final | 3/9/2026 | Corrections Issued | ARTHUR NEGRETE |
| HVAC-Final | 3/9/2026 | Approved | ARTHUR NEGRETE |
| PLUMBING-Final | 3/9/2026 | Approved | ARTHUR NEGRETE |
| Final | 4/13/2026 | OK to Issue CofO | ARTHUR NEGRETE |