1480 1/2 W 46TH ST 90062
Certificate Information: 1480 1/2 W 46TH ST 90062
- Application / Permit
- 25016-70000-17131
- Plan Check / Job No.
- B25SL00559
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Convert deatached garage into and ADU per 65852.2(e)(1)(A)
- Permit Issued
- Issued on 8/14/2025
- Issuing Office
- South Los Angeles
- Current Status
- Issued on 8/14/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 5/27/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 5/27/2025 | RICARDO RAMIREZ |
| Corrections Issued | 5/27/2025 | RICARDO RAMIREZ |
| Plan Check Approved | 8/5/2025 | RICARDO RAMIREZ |
| Issued | 8/14/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 6/14/2025 | CINDY QI |
| Sewer availability | Cleared | 6/14/2025 | CINDY QI |
| Eng Process Fee Ord 176,300 | Cleared | 7/3/2025 | CINDY QI |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| BARRY HACHE, (213) 202-9851 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 9/12/2025 | Approved | BARRY HACHE |
| Excavation/Setback/Form/Re-Bar | 10/2/2025 | Partial Approval | BARRY HACHE |
| Sewer | 10/2/2025 | Approved | BARRY HACHE |
| Excavation/Setback/Form/Re-Bar | 10/14/2025 | Approved | RAUL BARAJAS |
| Footing/Foundation/Slab | 10/14/2025 | Approved | RAUL BARAJAS |
| BUILDING-Rough-Frame | 11/6/2025 | Not Ready for Inspection | BARRY HACHE |
| Green Building Rough | 11/6/2025 | Not Ready for Inspection | BARRY HACHE |
| Verify Rec and Parks Fee Memo | 11/6/2025 | Not Ready for Inspection | BARRY HACHE |
| ELECTRICAL-Rough | 11/21/2025 | Corrections Issued | BARRY HACHE |
| HVAC-Rough | 11/21/2025 | Corrections Issued | BARRY HACHE |
| PLUMBING-Rough | 11/21/2025 | Approved | BARRY HACHE |
| ELECTRICAL-Rough | 12/9/2025 | Approved | BARRY HACHE |
| HVAC-Rough | 12/9/2025 | Approved | BARRY HACHE |
| Interior/Exterior Lathing | 12/9/2025 | Partial Approval | BARRY HACHE |
| Gas Test | 12/19/2025 | Approved | RAUL BARAJAS |
| Verify Rec and Parks Fee Memo | 12/19/2025 | Approved | RAUL BARAJAS |
| BUILDING-Rough-Frame | 1/2/2026 | Approved | JOSH MEISTER |
| Green Building Rough | 1/2/2026 | Approved | JOSH MEISTER |
| Insulation | 1/28/2026 | Corrections Issued | ALEX COLIN |
| Floor/Roof Diaphrgm/Shear Wall | 2/9/2026 | Approved | BARRY HACHE |
| Insulation | 2/9/2026 | Approved | BARRY HACHE |
| Shower Pan | 2/9/2026 | Approved | BARRY HACHE |
| Verify Rec and Parks Fee Memo | 2/9/2026 | Not Ready for Inspection | BARRY HACHE |
| Drywall Nailing | 2/13/2026 | Approved | BARRY HACHE |
| Interior/Exterior Lathing | 2/13/2026 | Approved | BARRY HACHE |
| Underground Mechanical | 6/4/2026 | Approved | LUIS CASTRO |
| Verify Rec and Parks Fee Memo | 6/4/2026 | Not Ready for Inspection | LUIS CASTRO |