444 E 31ST ST 90011
Certificate Information: 444 E 31ST ST 90011
- Application / Permit
- 25016-70000-05983
- Plan Check / Job No.
- B25SL00198
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Remodel to single family dwelling to create additional bedroom and relocate bathroom and remodel kitchen.
- Permit Issued
- Issued on 4/1/2025
- Issuing Office
- South Los Angeles
- Current Status
- Permit Finaled on 9/6/2025
Permit Application Status History
| Submitted | 3/4/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 3/4/2025 | RICARDO RAMIREZ |
| Corrections Issued | 3/4/2025 | RICARDO RAMIREZ |
| Plan Check Approved | 3/13/2025 | RICARDO RAMIREZ |
| Issued | 4/1/2025 | APPLICANT |
| Permit Finaled | 9/5/2025 | ALEJANDRO DE ARTOLA |
Permit Application Clearance Information
| Historic Resource Verification | Cleared | 3/10/2025 | YASMINE BASHIRI |
| Redevelopment Project Area | Cleared | 3/10/2025 | YASMINE BASHIRI |
| ZI | Cleared | 3/10/2025 | YASMINE BASHIRI |
| Eng Process Fee Ord 176,300 | Cleared | 3/11/2025 | ADRIAN SANCHEZ |
| Sewer availability | Cleared | 3/11/2025 | CHRISTINA BRACO |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| ALEJANDRO DE ARTOLA, (213) 202-3128 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| ELECTRICAL-Rough | 4/25/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Rough | 4/25/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 4/25/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Rough | 4/30/2025 | Approved | ALEJANDRO DE ARTOLA |
| HVAC-Rough | 4/30/2025 | Approved | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 4/30/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 5/1/2025 | Approved | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 5/1/2025 | Approved | ALEJANDRO DE ARTOLA |
| Insulation | 5/20/2025 | Approved | ALEJANDRO DE ARTOLA |
| Drywall Nailing | 5/28/2025 | Approved | ALEJANDRO DE ARTOLA |
| Interior/Exterior Lathing | 5/28/2025 | Partial Approval | ALEJANDRO DE ARTOLA |
| Shower Pan | 5/28/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Shower Pan | 6/2/2025 | Approved | JOSH MEISTER |
| Interior/Exterior Lathing | 6/10/2025 | Approved | ANTHONY RAMOS |
| Underground Mechanical | 6/27/2025 | Approved | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 8/11/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Final | 8/11/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Service/Power Release | 8/11/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 8/12/2025 | Approved | ALEJANDRO DE ARTOLA |
| Final | 8/12/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Gas Test | 8/12/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Final | 8/12/2025 | Approved | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 8/12/2025 | Approved | ALEJANDRO DE ARTOLA |
| SGSOV-Seismic Gas S/O Valve | 8/12/2025 | SGSOV Approved | ALEJANDRO DE ARTOLA |
| Service/Power Release | 8/12/2025 | Approved | ALEJANDRO DE ARTOLA |
| Smoke Detectors | 8/12/2025 | Approved | ALEJANDRO DE ARTOLA |
| Final | 8/13/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Gas Test | 8/13/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Final | 9/5/2025 | Permit Finaled | ALEJANDRO DE ARTOLA |
| Gas Test | 9/5/2025 | Approved | ALEJANDRO DE ARTOLA |