1511 1/2 W 50TH ST 90062
Certificate Information: 1511 1/2 W 50TH ST 90062
- Application / Permit
- 25016-70000-02709
- Plan Check / Job No.
- B25SL00072
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- Convert portion of first floor garage to ADU PER LAMC 12.22 A.33(c) and (e). Structural upgrades to building per engineer specifications.
- Permit Issued
- Issued on 4/24/2025
- Issuing Office
- South Los Angeles
- Current Status
- CofO Issued on 4/3/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/30/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 1/31/2025 | RICARDO RAMIREZ |
| Corrections Issued | 2/1/2025 | RICARDO RAMIREZ |
| Plan Check Approved | 4/15/2025 | RICARDO RAMIREZ |
| Issued | 4/24/2025 | APPLICANT |
| Building Plans Picked Up | 5/20/2025 | APPLICANT |
| CofO in Progress | 3/6/2026 | BARRY HACHE |
| No Progress | 3/13/2026 | DEROLD HAUFF |
| CofO in Progress | 3/13/2026 | DEROLD HAUFF |
| Permit Finaled | 4/3/2026 | DEROLD HAUFF |
| CofO Issued | 4/3/2026 | DEROLD HAUFF |
| Permit Finaled | 4/3/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| Construction near power lines | Cleared | 3/29/2025 | RIDWAN HARDY |
| Address approval | Cleared | 4/9/2025 | RYAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 4/9/2025 | RYAN CASTRO |
| Sewer availability | Cleared | 4/9/2025 | RYAN CASTRO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Madero,, Fidencio; Lic. No.: C81695 | PO BOX 40237 DOWNEY, CA 90239 |
Inspector Information
| BARRY HACHE, (213) 202-9851 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 6/18/2025 | Corrections Issued | BARRY HACHE |
| Excavation/Setback/Form/Re-Bar | 6/24/2025 | Partial Approval | BARRY HACHE |
| PLUMBING-Rough | 7/8/2025 | Approved | BARRY HACHE |
| Excavation/Setback/Form/Re-Bar | 7/16/2025 | Approved | BARRY HACHE |
| ELECTRICAL-Final | 8/13/2025 | Corrections Issued | BARRY HACHE |
| PLUMBING-Rough | 8/13/2025 | Corrections Issued | BARRY HACHE |
| Wood Frame | 8/13/2025 | Not Ready for Inspection | BARRY HACHE |
| ELECTRICAL-Rough | 8/26/2025 | Approved | BARRY HACHE |
| HVAC-Rough | 8/26/2025 | Approved | BARRY HACHE |
| PLUMBING-Rough | 8/26/2025 | Corrections Issued | BARRY HACHE |
| Floor/Roof Diaphrgm/Shear Wall | 9/3/2025 | Corrections Issued | BARRY HACHE |
| PLUMBING-Rough | 9/3/2025 | Approved | BARRY HACHE |
| Floor/Roof Diaphrgm/Shear Wall | 10/6/2025 | Approved | BARRY HACHE |
| BUILDING-Rough-Frame | 10/8/2025 | Approved | BARRY HACHE |
| Interior/Exterior Lathing | 10/8/2025 | Approved | BARRY HACHE |
| Insulation | 10/15/2025 | Approved | ALEX COLIN |
| Drywall Nailing | 10/24/2025 | Approved | BARRY HACHE |
| Interior/Exterior Lathing | 10/24/2025 | Approved | BARRY HACHE |
| HVAC-Final | 1/26/2026 | Corrections Issued | BARRY HACHE |
| PLUMBING-Final | 1/26/2026 | Corrections Issued | BARRY HACHE |
| ELECTRICAL-Final | 2/3/2026 | Corrections Issued | BARRY HACHE |
| PLUMBING-Final | 2/3/2026 | Approved | BARRY HACHE |
| ELECTRICAL-Final | 2/19/2026 | Corrections Issued | JOSH MEISTER |
| HVAC-Final | 2/19/2026 | Corrections Issued | JOSH MEISTER |
| ELECTRICAL-Final | 2/24/2026 | Approved | BARRY HACHE |
| HVAC-Final | 2/24/2026 | Approved | BARRY HACHE |
| SGSOV-Seismic Gas S/O Valve | 2/24/2026 | SGSOV Not Ready | BARRY HACHE |
| Smoke Detectors | 2/24/2026 | Corrections Issued | BARRY HACHE |
| Final | 3/2/2026 | Corrections Issued | BARRY HACHE |
| SGSOV-Seismic Gas S/O Valve | 3/2/2026 | SGSOV Approved | BARRY HACHE |
| Smoke Detectors | 3/2/2026 | Approved | BARRY HACHE |
| Final | 3/6/2026 | OK to Issue CofO | BARRY HACHE |
| Green Building Final | 3/6/2026 | Approved | BARRY HACHE |
| Service/Power Release | 3/6/2026 | Approved | BARRY HACHE |
| Underground Mechanical | 3/6/2026 | Approved | BARRY HACHE |