900 S KENMORE AVE PH#1 90006
Certificate Information: 900 S KENMORE AVE PH#1 90006
- Application / Permit
- 25016-40000-28161
- Plan Check / Job No.
- B25SP02932
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- Addtion and Convert (E) Attic on 6th floor to (N) Sunroom and Playroom on (E) 6 story Apt Building.
- Permit Issued
- Issued on 1/15/2026
- Issuing Office
- Metro
- Current Status
- Issued on 1/15/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 9/18/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 9/25/2025 | SERGIO GUTIERREZ |
| Assigned to Zoning Architect | 9/25/2025 | HAYDON CHAN |
| Corrections Issued | 9/30/2025 | SERGIO GUTIERREZ |
| Quality Review Completed | 10/8/2025 | KEN GILL |
| Green Plans Picked Up | 12/8/2025 | APPLICANT |
| Plan Check Approved | 1/13/2026 | SERGIO GUTIERREZ |
| Issued | 1/15/2026 | APPLICANT |
Permit Application Clearance Information
| Tenant Habitability Plan | Cleared | 10/15/2025 | KORNEL LELEA |
| Miscellaneous | Cleared | 10/17/2025 | FIPE LEILUA |
| Miscellaneous | Cleared | 10/22/2025 | DANIEL CORONADO |
| Sewer availability | Cleared | 10/30/2025 | DERRICK MAGEE |
| Eng Process Fee Ord 176,300 | Cleared | 10/31/2025 | DERRICK MAGEE |
| Historic Resource Verification | Cleared | 11/4/2025 | LAMBERT GIESSINGER |
| Green Code | Cleared | 11/18/2025 | SERGIO GUTIERREZ |
| ZA Case | Cleared | 12/2/2025 | DANIEL CORONADO |
| Redevelopment Project Area | Cleared | 12/3/2025 | YASMINE BASHIRI |
| Fire Marshal Fire Life Safety | Cleared | 12/10/2025 | MENOA AGHAJANI |
| Zoning Plan Check | Cleared | 12/10/2025 | HAYDON CHAN |
| DAS Clearance | Cleared | 12/11/2025 | SERGIO GUTIERREZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JEROME BLACKWOOD, (213) 213-5353 | Office Hours: 7:00-8:00 AM MON-FRI |
| REGINA MENDEZ, (213) 213-5353 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Wood Frame | 2/12/2026 | Partial Approval | JEROME BLACKWOOD |
| Drywall Nailing | 2/18/2026 | Partial Approval | JEROME BLACKWOOD |