1630 W 27TH ST 90732
Certificate Information: 1630 W 27TH ST 90732
- Application / Permit
- 25016-40000-09675
- Plan Check / Job No.
- B25SP00976
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT ATTACHED GARAGE INTO A.D.U. PER STATE LAW (GCS 66323(a)(1)) COMPLY WITH DEPT. ORDER DATED 3/5/2025. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE.
- Permit Issued
- Issued on 5/29/2025
- Issuing Office
- San Pedro
- Current Status
- CofO Issued on 10/14/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/1/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 4/1/2025 | LAWRENCE QUIRANTE |
| Corrections Issued | 4/2/2025 | LAWRENCE QUIRANTE |
| Building Plans Picked Up | 4/8/2025 | APPLICANT |
| Applicant returned to address corrections | 5/20/2025 | LAWRENCE QUIRANTE |
| Applicant returned to address corrections | 5/27/2025 | TSE MING HUANG |
| Plan Check Approved | 5/29/2025 | TSE MING HUANG |
| Issued | 5/29/2025 | APPLICANT |
| CofO in Progress | 9/3/2025 | PAUL REECE |
| Permit Finaled | 10/14/2025 | CLAUDIO MORENO |
| Permit Finaled | 10/14/2025 | CLAUDIO MORENO |
| CofO Issued | 10/14/2025 | CLAUDIO MORENO |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 5/20/2025 | LANNY MERRICK |
| Address approval | Cleared | 5/22/2025 | XOCHITL ARQUIETA |
| Eng Process Fee Ord 176,300 | Cleared | 5/29/2025 | XOCHITL ARQUIETA |
| Sewer availability | Cleared | 5/29/2025 | XOCHITL ARQUIETA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| KELLY WARNER, (310) 732-4530 | Office Hours: 7:00-8:00 AM MON-FRI |
| PAUL BECKER, (310) 732-4530 | Office Hours: 7:00-8:00 AM MON-FRI |
| KEITH EDGHILL, (310) 732-4530 | Office Hours: 7:00-8:00 AM MON-FRI |
| DANIEL GONZALEZ, (310) 732-4530 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 6/26/2025 | Approved | PAUL REECE |
| ELECTRICAL-Final | 7/24/2025 | Approved | PAUL REECE |
| ELECTRICAL-Rough | 7/24/2025 | Approved | PAUL REECE |
| HVAC-Final | 7/24/2025 | Approved | PAUL REECE |
| PLUMBING-Final | 7/24/2025 | Approved | PAUL REECE |
| Deputy Wood Construction | 7/25/2025 | Conditional Approval | PAUL REECE |
| Drywall Nailing | 7/30/2025 | Approved | PAUL REECE |
| Deputy Wood Construction | 7/31/2025 | Approved | PAUL REECE |
| Interior/Exterior Lathing | 8/4/2025 | Approved | PAUL REECE |
| BUILDING-Rough-Frame | 8/19/2025 | Approved | PAUL REECE |
| ELECTRICAL-Final | 8/19/2025 | Approved | PAUL REECE |
| Final | 8/19/2025 | Conditional Approval | PAUL REECE |
| Green Building Final | 8/19/2025 | Approved | PAUL REECE |
| Green Building Rough | 8/19/2025 | Approved | PAUL REECE |
| HVAC-Final | 8/19/2025 | Approved | PAUL REECE |
| PLUMBING-Final | 8/19/2025 | Approved | PAUL REECE |
| SGSOV-Seismic Gas S/O Valve | 8/19/2025 | SGSOV No Gas | PAUL REECE |
| Smoke Detectors | 8/19/2025 | Approved | PAUL REECE |
| Final | 9/3/2025 | OK to Issue CofO | PAUL REECE |