600 S WARNER AVE 90024
Certificate Information: 600 S WARNER AVE 90024
- Application / Permit
- 25016-30001-02019
- Plan Check / Job No.
- B25WL05154
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Supplemental ref to pcis # 25016-30000-02019, for 2 story addition to (e) 2-story S.F.D. and minor remodel of a half bath.
- Permit Issued
- Issued on 8/25/2025
- Issuing Office
- Valley
- Current Status
- Issued on 8/25/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 6/23/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 6/24/2025 | RICHARD GARCIA |
| Corrections Issued | 6/25/2025 | RICHARD GARCIA |
| Building Plans Picked Up | 7/3/2025 | APPLICANT |
| Plan Check Approved | 8/5/2025 | CAROLEAN BASMA |
| Issued | 8/25/2025 | APPLICANT |
Permit Application Clearance Information
| Specific Plan | Cleared | 7/21/2025 | EDUARDO HERMOSO |
| Grading Pre-Inspection | Cleared | 7/21/2025 | LANNY MERRICK |
| Eng Process Fee Ord 176,300 | Cleared | 7/31/2025 | BIAINA HARITUNIAN |
| Roof/Waste drainage to street | Cleared | 7/31/2025 | BIAINA HARITUNIAN |
Contact Information
| Architect | Goodman,, Benjamin Isaac; Lic. No.: C35193 | 1952 HILLCREST DRIVE LOS ANGELES, CA 90016 |
| Contractor | Voshall Construction Inc; Lic. No.: 920839-B | 9909 TOPANGA CANYON #102 CHATSWORTH, CA 91311 |
| Engineer | Yamini,, Soly; Lic. No.: C33719 | 540 WARNER AVE LOS ANGELES, CA 90024 |
Inspector Information
| DAVID SCANTLIN, (310) 914-3863 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 8/27/2025 | Not Ready for Inspection | DANIEL VERA |
| Footing/Foundation/Slab | 9/10/2025 | Corrections Issued | DANIEL VERA |
| BUILDING-Rough-Frame | 12/11/2025 | Partial Approval | EVAN COOPER |
| ELECTRICAL-Rough | 12/11/2025 | Corrections Issued | EVAN COOPER |
| Green Building Rough | 12/11/2025 | Not Ready for Inspection | EVAN COOPER |
| ELECTRICAL-Rough | 12/12/2025 | Not Ready for Inspection | CARLOS MATAMOROS |
| HVAC-Rough | 12/12/2025 | Not Ready for Inspection | CARLOS MATAMOROS |
| PLUMBING-Rough | 12/12/2025 | Not Ready for Inspection | CARLOS MATAMOROS |
| BUILDING-Rough-Frame | 12/16/2025 | Not Ready for Inspection | DANIEL VERA |
| ELECTRICAL-Rough | 12/16/2025 | Not Ready for Inspection | DANIEL VERA |
| Green Building Rough | 12/16/2025 | Not Ready for Inspection | DANIEL VERA |
| HVAC-Rough | 12/16/2025 | Not Ready for Inspection | DANIEL VERA |
| Interior/Exterior Lathing | 12/16/2025 | Partial Approval | DANIEL VERA |
| PLUMBING-Rough | 12/16/2025 | Not Ready for Inspection | DANIEL VERA |
| Interior/Exterior Lathing | 12/24/2025 | Partial Approval | EVAN COOPER |
| HVAC-Rough | 1/23/2026 | Not Ready for Inspection | CHRISTOPHER WILSON |
| PLUMBING-Rough | 1/23/2026 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Wood Frame | 1/23/2026 | Not Ready for Inspection | CHRISTOPHER WILSON |
| BUILDING-Rough-Frame | 1/26/2026 | Not Ready for Inspection | CHRISTOPHER WILSON |
| HVAC-Rough | 1/26/2026 | Approved | CHRISTOPHER WILSON |
| ELECTRICAL-Rough | 1/28/2026 | Approved | RYAN SALAZAR |
| PLUMBING-Rough | 1/28/2026 | Approved | RYAN SALAZAR |
| Insulation | 2/23/2026 | Approved | CHRISTOPHER WILSON |
| Drywall Nailing | 3/24/2026 | Approved | CHRISTOPHER WILSON |
| Green Building Rough | 3/24/2026 | Approved | CHRISTOPHER WILSON |