600 S WARNER AVE 90024

Certificate Information: 600 S WARNER AVE 90024

Application / Permit
25016-30001-02019
Plan Check / Job No.
B25WL05154
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Supplemental ref to pcis # 25016-30000-02019, for 2 story addition to (e) 2-story S.F.D. and minor remodel of a half bath.
Permit Issued
Issued on 8/25/2025
Issuing Office
Valley
Current Status
Issued on 8/25/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 6/23/2025 APPLICANT
Assigned to Plan Check Engineer 6/24/2025 RICHARD GARCIA
Corrections Issued 6/25/2025 RICHARD GARCIA
Building Plans Picked Up 7/3/2025 APPLICANT
Plan Check Approved 8/5/2025 CAROLEAN BASMA
Issued 8/25/2025 APPLICANT

Permit Application Clearance Information

Specific Plan Cleared 7/21/2025 EDUARDO HERMOSO
Grading Pre-Inspection Cleared 7/21/2025 LANNY MERRICK
Eng Process Fee Ord 176,300 Cleared 7/31/2025 BIAINA HARITUNIAN
Roof/Waste drainage to street Cleared 7/31/2025 BIAINA HARITUNIAN

Contact Information

Architect Goodman,, Benjamin Isaac; Lic. No.: C35193 1952 HILLCREST DRIVE      LOS ANGELES, CA 90016
Contractor Voshall Construction Inc; Lic. No.: 920839-B 9909 TOPANGA CANYON #102      CHATSWORTH, CA 91311
Engineer Yamini,, Soly; Lic. No.: C33719 540 WARNER AVE      LOS ANGELES, CA 90024

Inspector Information

DAVID SCANTLIN, (310) 914-3863 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 8/27/2025 Not Ready for Inspection DANIEL VERA
Footing/Foundation/Slab 9/10/2025 Corrections Issued DANIEL VERA
BUILDING-Rough-Frame 12/11/2025 Partial Approval EVAN COOPER
ELECTRICAL-Rough 12/11/2025 Corrections Issued EVAN COOPER
Green Building Rough 12/11/2025 Not Ready for Inspection EVAN COOPER
ELECTRICAL-Rough 12/12/2025 Not Ready for Inspection CARLOS MATAMOROS
HVAC-Rough 12/12/2025 Not Ready for Inspection CARLOS MATAMOROS
PLUMBING-Rough 12/12/2025 Not Ready for Inspection CARLOS MATAMOROS
BUILDING-Rough-Frame 12/16/2025 Not Ready for Inspection DANIEL VERA
ELECTRICAL-Rough 12/16/2025 Not Ready for Inspection DANIEL VERA
Green Building Rough 12/16/2025 Not Ready for Inspection DANIEL VERA
HVAC-Rough 12/16/2025 Not Ready for Inspection DANIEL VERA
Interior/Exterior Lathing 12/16/2025 Partial Approval DANIEL VERA
PLUMBING-Rough 12/16/2025 Not Ready for Inspection DANIEL VERA
Interior/Exterior Lathing 12/24/2025 Partial Approval EVAN COOPER
HVAC-Rough 1/23/2026 Not Ready for Inspection CHRISTOPHER WILSON
PLUMBING-Rough 1/23/2026 Not Ready for Inspection CHRISTOPHER WILSON
Wood Frame 1/23/2026 Not Ready for Inspection CHRISTOPHER WILSON
BUILDING-Rough-Frame 1/26/2026 Not Ready for Inspection CHRISTOPHER WILSON
HVAC-Rough 1/26/2026 Approved CHRISTOPHER WILSON
ELECTRICAL-Rough 1/28/2026 Approved RYAN SALAZAR
PLUMBING-Rough 1/28/2026 Approved RYAN SALAZAR
Insulation 2/23/2026 Approved CHRISTOPHER WILSON
Drywall Nailing 3/24/2026 Approved CHRISTOPHER WILSON
Green Building Rough 3/24/2026 Approved CHRISTOPHER WILSON