1820 S PROSSER AVE 1-9 90025
Certificate Information: 1820 S PROSSER AVE 1-9 90025
- Application / Permit
- 25016-30000-34684
- Plan Check / Job No.
- B25WL09143
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Conversion of an (e) recreation room intoan ADU per LAMC12.22A.33(c) and(e)
- Permit Issued
- Issued on 1/6/2026
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 3/24/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/24/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 12/2/2025 | RICHARD GARCIA |
| Corrections Issued | 12/3/2025 | RICHARD GARCIA |
| Building Plans Picked Up | 12/5/2025 | APPLICANT |
| Plan Check Approved | 12/22/2025 | AMY GUEVARRA |
| Issued | 1/6/2026 | APPLICANT |
| CofO in Progress | 3/24/2026 | VASIL MIHALEV |
| Permit Finaled | 3/24/2026 | VASIL MIHALEV |
| CofO Issued | 3/24/2026 | VASIL MIHALEV |
| Permit Finaled | 3/24/2026 | VASIL MIHALEV |
Permit Application Clearance Information
| Specific Plan | Cleared | 12/16/2025 | RICHARD WOO |
| Address approval | Cleared | 12/17/2025 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 12/17/2025 | CARLOS AGUILERA |
Contact Information
| Contractor | Aram Construction Company; Lic. No.: 934479-B | 8500 WILSHIRE BLVD # 509 BEVERLY HILLS, CA 90211 |
Inspector Information
| ROGELIO REYNA, (310) 914-3920 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 1/12/2026 | Corrections Issued | CASIMIR BRITTON |
| Pre-Inspection | 1/12/2026 | Partial Inspection | ROGELIO REYNA |
| Interior/Exterior Lathing | 2/2/2026 | Not Ready for Inspection | ROGELIO REYNA |
| METHANE-Rough | 2/2/2026 | Approved | ROGELIO REYNA |
| Wood Frame | 2/2/2026 | Partial Approval | ROGELIO REYNA |
| Insulation | 2/4/2026 | Approved | ROGELIO REYNA |
| Interior/Exterior Lathing | 2/4/2026 | Approved | ROGELIO REYNA |
| Drywall Nailing | 2/5/2026 | Approved | ROGELIO REYNA |
| Final | 3/20/2026 | Partial Inspection | ROGELIO REYNA |
| SGSOV-Seismic Gas S/O Valve | 3/20/2026 | SGSOV Approved | ROGELIO REYNA |
| Smoke Detectors | 3/20/2026 | Approved | ROGELIO REYNA |
| Wood Frame | 3/20/2026 | Approved | ROGELIO REYNA |
| Final | 3/24/2026 | OK to Issue CofO | VASIL MIHALEV |