2629 W SUNLIGHT PL 90016
Certificate Information: 2629 W SUNLIGHT PL 90016
- Application / Permit
- 25016-30000-30950
- Plan Check / Job No.
- B25WL08228
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Convert (e) 2 car garage into an ADU per LAMC 12.22 A.33(c)(e)(d)
- Permit Issued
- Issued on 1/20/2026
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 5/5/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/16/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 10/21/2025 | RICHARD GARCIA |
| Corrections Issued | 10/22/2025 | RICHARD GARCIA |
| Building Plans Picked Up | 10/24/2025 | APPLICANT |
| Plan Check Approved | 1/8/2026 | DAVID CASTILLO |
| Issued | 1/20/2026 | APPLICANT |
| CofO in Progress | 5/2/2026 | WILLIAM SIERRA |
| CofO Issued | 5/5/2026 | DEROLD HAUFF |
| Permit Finaled | 5/5/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 11/8/2025 | DARIN LAM |
| Roof/Waste drainage to street | Cleared | 11/8/2025 | DARIN LAM |
| Sewer availability | Cleared | 11/8/2025 | DARIN LAM |
| Construction near power lines | Cleared | 12/22/2025 | RIDWAN HARDY |
| Eng Process Fee Ord 176,300 | Cleared | 12/31/2025 | DARIN LAM |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Garcia,, Francisco Diaz; Lic. No.: C88029 | 19145 MALABAR ST SANTA CLARITA, CA 91351 |
Inspector Information
| DAVID WILLIAMS, (213) 202-3126 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 1/22/2026 | Corrections Issued | BRENDAN MORELLI |
| Footing/Foundation/Slab | 2/3/2026 | Approved | BRENDAN MORELLI |
| Underground Mechanical | 2/3/2026 | Corrections Issued | BRENDAN MORELLI |
| SGSOV-Seismic Gas S/O Valve | 3/5/2026 | SGSOV Approved | BRENDAN MORELLI |
| Underground Mechanical | 3/5/2026 | Partial Approval | BRENDAN MORELLI |
| BUILDING-Rough-Frame | 4/15/2026 | Approved | BRENDAN MORELLI |
| Final | 4/15/2026 | Corrections Issued | BRENDAN MORELLI |
| Green Building Final | 4/15/2026 | Not Ready for Inspection | BRENDAN MORELLI |
| Green Building Rough | 4/15/2026 | Approved | BRENDAN MORELLI |
| Smoke Detectors | 4/15/2026 | Corrections Issued | BRENDAN MORELLI |
| Final | 4/20/2026 | Corrections Issued | WILLIAM SIERRA |
| Green Building Final | 4/20/2026 | Not Ready for Inspection | WILLIAM SIERRA |
| Smoke Detectors | 4/20/2026 | Approved | WILLIAM SIERRA |
| Final | 4/28/2026 | Corrections Issued | WILLIAM SIERRA |
| Green Building Final | 4/28/2026 | Approved | WILLIAM SIERRA |
| Final | 5/1/2026 | OK to Issue CofO | WILLIAM SIERRA |