3639 S VIRGINIA ROAD 90016

Certificate Information: 3639 S VIRGINIA ROAD 90016

Application / Permit
25016-30000-27481
Plan Check / Job No.
B25WL07404
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) DETACHED GARAGE TO AN ACCESSORY DWELLING UNIT PER GC 66323(a)(1) ALL WORK PER WFPP "COMPLY WITH DEPARTMENT ORDER effective date 09/09/2025. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE"
Permit Issued
Issued on 11/20/2025
Issuing Office
Metro
Current Status
Issued on 11/20/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 9/11/2025 APPLICANT
Assigned to Plan Check Engineer 9/12/2025 REZA HAGHIGHAT
Corrections Issued 9/12/2025 REZA HAGHIGHAT
Building Plans Picked Up 9/18/2025 APPLICANT
Applicant returned to address corrections 10/8/2025 NAREG ATARIAN
Plan Check Approved 11/3/2025 SEWADA ZADOORAN MILAGARDI
Issued 11/20/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 9/18/2025 XOCHITL ARQUIETA
Eng Process Fee Ord 176,300 Cleared 9/18/2025 XOCHITL ARQUIETA
Sewer availability Cleared 9/18/2025 XOCHITL ARQUIETA
Construction near power lines Cleared 10/31/2025 RIDWAN HARDY

Contact Information

Contractor Sunny Homes Remodeling; Lic. No.: 1118950-B-2 21981 GRASS VALLEY      MISSION VIEJO, CA 92692

Inspector Information

LUIS CORRAL, (213) 252-3964 Office Hours: 7:00-8:00 AM MON-FRI
DONALD WONG, (213) 252-3964 Office Hours: 7:00-8:00 AM MON-FRI
KIM DOEPPING, (213) 252-3964 Office Hours: 7:00-8:00 AM MON-FRI
WILLIAM MICHALAK, (213) 252-3964 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 12/2/2025 No Access for Inspection WILLIAM MICHALAK
Drywall Nailing 12/2/2025 No Access for Inspection WILLIAM MICHALAK
Final 12/2/2025 Not Ready for Inspection WILLIAM MICHALAK
Green Building Final 12/2/2025 No Access for Inspection WILLIAM MICHALAK
Green Building Rough 12/2/2025 No Access for Inspection WILLIAM MICHALAK
SGSOV-Seismic Gas S/O Valve 12/2/2025 SGSOV Not Ready WILLIAM MICHALAK
Smoke Detectors 12/2/2025 No Access for Inspection WILLIAM MICHALAK
BUILDING-Rough-Frame 12/4/2025 Corrections Issued WILLIAM MICHALAK
Drywall Nailing 12/4/2025 Corrections Issued WILLIAM MICHALAK
Final 12/4/2025 Corrections Issued WILLIAM MICHALAK
Green Building Final 12/4/2025 Corrections Issued WILLIAM MICHALAK
Green Building Rough 12/4/2025 Corrections Issued WILLIAM MICHALAK
SGSOV-Seismic Gas S/O Valve 12/4/2025 SGSOV Not Ready WILLIAM MICHALAK
Smoke Detectors 12/4/2025 Corrections Issued WILLIAM MICHALAK
Footing/Foundation/Slab 12/11/2025 Corrections Issued WILLIAM MICHALAK
Excavation/Setback/Form/Re-Bar 12/22/2025 Corrections Issued WILLIAM MICHALAK
Footing/Foundation/Slab 12/22/2025 Corrections Issued WILLIAM MICHALAK
Excavation/Setback/Form/Re-Bar 12/23/2025 Approved WILLIAM MICHALAK
Footing/Foundation/Slab 12/23/2025 Approved WILLIAM MICHALAK
BUILDING-Rough-Frame 12/30/2025 Not Ready for Inspection WILLIAM MICHALAK
Green Building Rough 12/30/2025 Not Ready for Inspection WILLIAM MICHALAK
SGSOV-Seismic Gas S/O Valve 12/30/2025 SGSOV Not Ready WILLIAM MICHALAK
BUILDING-Rough-Frame 1/21/2026 Corrections Issued LUIS CORRAL
Drywall Nailing 1/21/2026 Not Ready for Inspection LUIS CORRAL
ELECTRICAL-Rough 1/21/2026 Corrections Issued LUIS CORRAL
Final 1/21/2026 Not Ready for Inspection LUIS CORRAL
Green Building Final 1/21/2026 Not Ready for Inspection LUIS CORRAL
Green Building Rough 1/21/2026 Not Ready for Inspection LUIS CORRAL
PLUMBING-Rough 1/21/2026 Corrections Issued LUIS CORRAL
SGSOV-Seismic Gas S/O Valve 1/21/2026 SGSOV Not Ready LUIS CORRAL
Smoke Detectors 1/21/2026 Not Ready for Inspection LUIS CORRAL
BUILDING-Rough-Frame 1/27/2026 Not Ready for Inspection WILLIAM MICHALAK
Drywall Nailing 1/27/2026 Not Ready for Inspection WILLIAM MICHALAK
Final 1/27/2026 Not Ready for Inspection WILLIAM MICHALAK
Green Building Final 1/27/2026 No Access for Inspection WILLIAM MICHALAK
Green Building Rough 1/27/2026 Not Ready for Inspection WILLIAM MICHALAK
SGSOV-Seismic Gas S/O Valve 1/27/2026 SGSOV Not Required WILLIAM MICHALAK
Smoke Detectors 1/27/2026 Not Ready for Inspection WILLIAM MICHALAK
BUILDING-Rough-Frame 2/3/2026 Not Ready for Inspection LUIS CORRAL
Drywall Nailing 2/3/2026 Not Ready for Inspection LUIS CORRAL
Final 2/3/2026 Not Ready for Inspection LUIS CORRAL
Green Building Final 2/3/2026 Not Ready for Inspection LUIS CORRAL
Green Building Rough 2/3/2026 Not Ready for Inspection LUIS CORRAL
PLUMBING-Rough 2/3/2026 Corrections Issued LUIS CORRAL
Smoke Detectors 2/3/2026 Not Ready for Inspection LUIS CORRAL
Floor/Roof Diaphrgm/Shear Wall 2/17/2026 Partial Approval WILLIAM MICHALAK
Drywall Nailing 2/26/2026 Partial Approval WILLIAM MICHALAK
Green Building Rough 2/26/2026 Corrections Issued WILLIAM MICHALAK
PLUMBING-Rough 2/27/2026 Approved LUIS CORRAL
Interior/Exterior Lathing 3/2/2026 Approved LUIS CORRAL
BUILDING-Rough-Frame 3/24/2026 Corrections Issued LUIS CORRAL
Drywall Nailing 3/24/2026 Approved LUIS CORRAL
Final 3/24/2026 Not Ready for Inspection LUIS CORRAL
Green Building Final 3/24/2026 Approved LUIS CORRAL
Green Building Rough 3/24/2026 Approved LUIS CORRAL
Smoke Detectors 3/24/2026 Approved LUIS CORRAL
BUILDING-Rough-Frame 4/1/2026 Approved LUIS CORRAL
Final 4/1/2026 Partial Approval LUIS CORRAL