141 S BOWLING GREEN WAY 90049

Certificate Information: 141 S BOWLING GREEN WAY 90049

Application / Permit
25016-30000-26420
Plan Check / Job No.
B25WL07102
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Addition and structural remodel of an (E) SFD. Adding new uncovered deck at front of house and a juliet balcony. Remodel of kitchen and dining area. New front entry facade. New attached rear trellis. ***SEE COMMENTS***
Permit Issued
Issued on 1/22/2026
Issuing Office
West Los Angeles
Current Status
Issued on 1/22/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 9/2/2025 APPLICANT
Assigned to Plan Check Engineer 9/2/2025 RICHARD GARCIA
Corrections Issued 9/3/2025 RICHARD GARCIA
Building Plans Picked Up 9/4/2025 APPLICANT
Applicant returned to address corrections 12/26/2025 CAROLEAN BASMA
Applicant returned to address corrections 1/8/2026 CAROLEAN BASMA
Plan Check Approved 1/20/2026 CAROLEAN BASMA
Issued 1/22/2026 APPLICANT

Permit Application Clearance Information

Grading Pre-Inspection Cleared 9/8/2025 LANNY MERRICK
Eng Process Fee Ord 176,300 Cleared 11/17/2025 SAFA JAVANMARDI
Roof/Waste drainage to street Cleared 11/21/2025 SAFA JAVANMARDI
Specific Plan Cleared 1/15/2026 EDER ROMERO
Trees in Parkway Cleared 1/15/2026 RICHARD SANCHEZ
Permit Cleared 1/16/2026 SAFA JAVANMARDI

Contact Information

Contractor Magnano Robert E Incorporated; Lic. No.: 590032-B 23525 CAVANAUGH ROAD      LAKE FOREST, CA 92630

Inspector Information

HERBERT GIRON, (310) 914-3891 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 1/29/2026 Partial Approval HERBERT GIRON
Deputy Reinf. Concrete 2/2/2026 Conditional Approval JUAN VALENZUELA
Deputy Reinf. Concrete 2/9/2026 Conditional Approval JUAN VALENZUELA
Excavation/Setback/Form/Re-Bar 2/12/2026 Approved HERBERT GIRON
Footing/Foundation/Slab 2/12/2026 Approved HERBERT GIRON
Reinforced Concrete Frame 2/12/2026 Approved HERBERT GIRON
Structural Steel Frame 2/12/2026 Partial Approval HERBERT GIRON
Deputy Reinf. Concrete 2/20/2026 Conditional Approval JUAN VALENZUELA
Footing/Foundation/Slab 2/20/2026 Approved HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 4/3/2026 Corrections Issued KEVIN SARGSYAN
PLUMBING-Rough 4/3/2026 Partial Approval KEVIN SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 4/8/2026 Approved HERBERT GIRON
PLUMBING-Rough 4/8/2026 Approved HERBERT GIRON
HVAC-Rough 4/15/2026 Conditional Approval HERBERT GIRON
ELECTRICAL-Rough 4/23/2026 Approved KEVIN SARGSYAN
BUILDING-Rough-Frame 4/28/2026 Partial Approval HERBERT GIRON
HVAC-Rough 4/28/2026 Approved HERBERT GIRON
Insulation 4/30/2026 Partial Approval KEVIN SARGSYAN
Shower Pan 4/30/2026 Approved KEVIN SARGSYAN
Drywall Nailing 5/7/2026 Partial Approval KEVIN SARGSYAN
Interior/Exterior Lathing 5/11/2026 Corrections Issued KEVIN SARGSYAN
Interior/Exterior Lathing 5/14/2026 Approved KEVIN SARGSYAN
Interior/Exterior Lathing 6/8/2026 Partial Approval RYAN SALAZAR
Drywall Nailing 6/10/2026 Approved KEVIN SARGSYAN