9018 W HARGIS ST 90034

Certificate Information: 9018 W HARGIS ST 90034

Application / Permit
25016-30000-24504
Plan Check / Job No.
B25WL06563
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Structural Remodel of an (E) SFD.
Permit Issued
Issued on 9/11/2025
Issuing Office
West Los Angeles
Current Status
Permit Finaled on 6/5/2026

Permit Application Status History

Submitted 8/12/2025 APPLICANT
Assigned to Plan Check Engineer 8/12/2025 JAHANSHAH POURHASSAN
Corrections Issued 8/13/2025 JAHANSHAH POURHASSAN
Building Plans Picked Up 8/14/2025 APPLICANT
Plan Check Approved 8/29/2025 CAROLEAN BASMA
Issued 9/11/2025 APPLICANT
Permit Finaled 6/4/2026 WILBER ROSALES

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 8/18/2025 WALLIE JONG
Roof/Waste drainage to street Cleared 8/18/2025 WALLIE JONG
Sewer availability Cleared 8/18/2025 WALLIE JONG
Grading Pre-Inspection Cleared 8/25/2025 LANNY MERRICK

Contact Information

Contractor Rimon Construction Inc; Lic. No.: 1077839-B 554 S SAN VICENTE BLVD STE 206      LOS ANGELES, CA 90046
Engineer Sivushenka,, Mikita; Lic. No.: C87698 22814 DOLOROSA ST      WOODLAND HILLS, CA 91367

Inspector Information

WILBER ROSALES, (310) 914-3892 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 9/15/2025 Corrections Issued EVAN COOPER
PLUMBING-Rough 9/15/2025 Corrections Issued EVAN COOPER
ELECTRICAL-Rough 9/25/2025 Approved EVAN COOPER
HVAC-Rough 9/25/2025 Not Ready for Inspection EVAN COOPER
PLUMBING-Rough 9/25/2025 Approved EVAN COOPER
Wood Frame 9/25/2025 Corrections Issued EVAN COOPER
Interior/Exterior Lathing 9/30/2025 Partial Approval EVAN COOPER
Shower Pan 9/30/2025 Approved EVAN COOPER
Insulation 10/10/2025 Partial Approval EVAN COOPER
Drywall Nailing 10/20/2025 Partial Approval EVAN COOPER
Interior/Exterior Lathing 11/6/2025 Partial Approval ASHLEY THOMPSON
ELECTRICAL-Final 5/7/2026 Approved WILBER ROSALES
Final 5/7/2026 Not Ready for Inspection WILBER ROSALES
HVAC-Final 5/7/2026 Approved WILBER ROSALES
PLUMBING-Final 5/7/2026 Approved WILBER ROSALES
SGSOV-Seismic Gas S/O Valve 5/7/2026 SGSOV Approved WILBER ROSALES
Smoke Detectors 5/7/2026 Approved WILBER ROSALES
Final 6/4/2026 Permit Finaled WILBER ROSALES